Skip to content
Brent$104.61Gas TTF$906USD446.56 ₸
MunaiHub
For operators

Field development stages

The path of an onshore oil field — from the auction and the exploration and production contract to liquidation and the return of the subsoil area to the state. The subsoil user's work, project documents, expert reviews, environmental and other permits — with the deadlines of state bodies and links to the laws.

stages
6
stages
steps, decisions and approvals
86
steps, decisions and approvals
approvals with a statutory deadline
32
approvals with a statutory deadline
years — the full cycle in a typical case
≈ 37
years — the full cycle in a typical case
  1. 01Obtaining the subsoil use rightBonus and contract within 20 working days of the auction
  2. 02ExplorationExploration period up to 6 years (18 for complex projects)
  3. 03Appraisal and trial productionWithin the 6-year exploration period
  4. 04Getting ready to producePreparatory period up to 3 years
  5. 05ProductionProduction period up to 25 years (45 for large fields)
  6. 06Liquidation and return of the areaStart within 6 months of the right ending

Gantt chart

Click a row to open the step's description, deadlines and legal basis. A stage can be opened full width.

Streams
Years from the contract signing (typical case)
-1 yContract1 y2 y3.5 y5 y6 y7 y8 y20 y33 y36 y
Subsoil user's work State review, permit or decision Event, decision point Repeats throughout the stage

Approvals and statutory deadlines

Every state review, conclusion, permit and decision in the order of the stages. The deadline is the time the law gives the state body; where the law sets none, the table says so.

1 Obtaining the subsoil use right
The area in the state subsoil fund programmeThe National geology operator, the Ministry of Industry and Construction, the Ministry of Energy15 working days — to consider proposals on area boundaries at each step of drawing up the ProgrammeSubsoil Code, Arts. 70, 94
The electronic auctionThe Ministry of Energy and the electronic auction operatorup to 2 months after applications close (10 working days for poorly studied territories)Subsoil Code, Arts. 95, 99, 100Hydrocarbon e-auction rules
Direct negotiations — instead of an auctionMinistry of Energy (the competent body)2 months for the negotiations from the application (can be extended)Subsoil Code, Arts. 103–105
2 Exploration
Notice of the planned activity and screeningMinistry of Ecology and Natural Resources (the environmental authority)22 working days from the registration of the noticeEnvironmental Code, Arts. 68, 69, 71
Environmental impact assessment of the explorationMinistry of Ecology and Natural Resources (the environmental authority)30 working days for the assessment conclusion from the registration of the applicationEnvironmental Code, Arts. 73, 76
Review of the exploration project by the central commissionThe Central Commission for Exploration and Development of Hydrocarbon Fields2 monthsCentral Commission (TsKRR) regulationSubsoil Code, Art. 140
Public easement over the land for explorationThe local executive body (akimat)No separate deadline is setLand Code, Arts. 69, 71-1
Integrated environmental permitMinistry of Ecology and Natural Resources (the environmental authority)The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working daysEnvironmental Code, Arts. 111, 113, 115, 117, 418
Special water use permitThe basin water inspectorate10 working daysWater Code (2025), Arts. 45, 46
Annual reports on the contract obligationsMinistry of Energy (the competent body)6 months to analyse the annual reportContract obligations monitoring rules
Report on exploration results for a poorly studied territoryThe Geology Committee (the authorised body for subsoil study)1 monthHydrocarbon geological report rules
Extending the exploration periodMinistry of Energy (the competent body)20 working daysSubsoil Code, Arts. 114, 117
3 Appraisal and trial production
Review of the addendum by the central commissionThe Central Commission for Exploration and Development of Hydrocarbon Fields2 monthsCentral Commission (TsKRR) regulation
Environmental assessment of trial productionMinistry of Ecology and Natural Resources (the environmental authority)22 working days for the screening conclusion; a full assessment takes up to 30 more working daysEnvironmental Code, Arts. 68, 69, 76
Review of the trial production projectThe Central Commission for Exploration and Development of Hydrocarbon Fields3 months (+ up to 3 months if extended)Central Commission (TsKRR) regulation
Integrated permit for trial productionMinistry of Ecology and Natural Resources (the environmental authority)The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working daysEnvironmental Code, Arts. 111, 115, 117
Raw gas processing development programmeThe Ministry of Energy (on the working group's recommendation)No separate deadline is setSubsoil Code, Art. 147Raw gas flaring permit rules
State review of the reservesThe State Commission on Mineral Reserves (Ministry of Industry and Construction)The deadline is set by the Commission's regulation (Order No. 171 of 15.05.2024) — check the current versionSubsoil Code, Arts. 141, 277
4 Getting ready to produce
Notice of the development and the assessment scopeMinistry of Ecology and Natural Resources (the environmental authority)22 working days from the registration of the noticeEnvironmental Code, Arts. 65, 71
Heritage survey before the land is allocatedA licensed expert under contract; a copy to the akimatup to 30 calendar days (the exact term is set by the contract)Law on the Protection and Use of Historical and Cultural Heritage, Art. 30Rules for historical and cultural expertise
Design inputs: the planning brief and utility conditionsThe akimat's architecture and planning body; utility ownersUntil 1 July 2026 — 6 working days for technically simple objects; check the deadlines under the rules of the new Construction CodeConstruction Code
Land for the production facilities: a lease for the contract termThe local executive body (akimat)up to 15 working days (not counting the land management project)Land Code, Arts. 37, 43
Environmental impact assessment conclusionMinistry of Ecology and Natural Resources (the environmental authority)30 working days from the registration of the applicationEnvironmental Code, Arts. 65, 76
Changing the designated use of the landThe local executive body (akimat)up to 16 working days outside settlements (up to 8 inside them)Land Code, Art. 49-1
Review of the development projectThe Central Commission for Exploration and Development of Hydrocarbon Fields3 months (+ up to 3 months if extended)Central Commission (TsKRR) regulationSubsoil Code, Art. 119
Water use at the fieldThe basin water inspectorate10 working daysWater Code (2025), Arts. 45, 46, 50
Integrated permit for the production facilitiesMinistry of Ecology and Natural Resources (the environmental authority)The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working daysEnvironmental Code, Arts. 111, 115, 117, 186
Comprehensive non-departmental design reviewThe state expert organisationUnder the rules in force until 1 July 2026 — 15 to 45 working days by complexity; check the deadlines under the new rulesConstruction Code, Art. 104Rules for the comprehensive non-departmental review of construction designs
Industrial safety of the designAn accredited expert firm; the state industrial safety inspector (Ministry of Emergency Situations)No separate deadline is setCivil Protection Law, Arts. 73, 78
Industrial safety declarationThe industrial safety authority (Ministry of Emergency Situations)No separate deadline is setCivil Protection Law, Art. 76
Moving to the production periodMinistry of Energy (the competent body)20 working days to consider the contract changeSubsoil Code, Arts. 14, 37, 119
5 Production
Annual contract reports — the ministry's analysisMinistry of Energy (the competent body)6 months to analyse the annual reportContract obligations monitoring rules
Author supervision and development analysisThe Central Commission for Exploration and Development of Hydrocarbon Fields3 months (+ up to 3 months if extended)Unified Rules on rational and integrated subsoil useCentral Commission (TsKRR) regulation
A new development project or an addendumThe Central Commission for Exploration and Development of Hydrocarbon Fields3 months (+ up to 3 months if extended)Unified Rules on rational and integrated subsoil useCentral Commission (TsKRR) regulation
Re-estimating the reservesThe State Commission on Mineral ReservesThe deadline is set by the Commission's regulation (Order No. 171 of 15.05.2024) — check the current versionSubsoil Code, Art. 141Reserves estimation methodologies
Extending the production periodMinistry of Energy (the competent body)2 monthsSubsoil Code, Art. 120
6 Liquidation and return of the area
Acceptance by a commission and the liquidation actA Ministry of Energy commission with the environmental, industrial safety, sanitary and geology bodies10 working days after inspecting the areaSubsoil Code, Art. 126Hydrocarbon suspension and abandonment rules
Returning the landThe local executive body (akimat)No separate deadline is setLand Code

The stages in detail

1

Obtaining the subsoil use right

The area is in the programme, the auction is won, the contract is signed and registered

By law
Bonus and contract within 20 working days of the auction
Typically
12 months
  1. Right and contractWork

    Choosing the area and studying the geological data

    The investor picks an area from the Programme for managing the state subsoil fund, studies the geological data available on the Unified subsoil use platform and in the funds of the National Geological Service, and weighs the prospects, infrastructure, risks and economics of the project.

    Result
    A decision to bid
  2. Right and contractApproval

    The area in the state subsoil fund programme

    An auction is held only for an area in the Programme. The National geology operator draws it up, the Ministry of Industry and Construction approves it and the Ministry of Energy agrees its hydrocarbon part; it is updated at least every six months. An investor does not apply to add an area — state bodies propose the boundaries; for an area already in the Programme the investor can initiate an auction.

    Who
    The National geology operator, the Ministry of Industry and Construction, the Ministry of Energy
    Statutory review time
    15 working days — to consider proposals on area boundaries at each step of drawing up the Programme
  3. Right and contractWork

    Applying to take part in the auction

    The notice is published on the auction operator's electronic platform. A bidder needs a digital signature, an entry fee (100 MCI) and a guarantee deposit securing the signature bonus.

    Time limit for the subsoil user
    2 months from the notice (10 working days for areas in poorly studied territories)
  4. Right and contractApproval

    The electronic auction

    Bids rise by the auction step; the bidder offering the highest signature bonus wins. If the only registered bidder is the one who initiated the auction, the auction is cancelled and the contract is concluded with it at the starting bonus.

    Who
    The Ministry of Energy and the electronic auction operator
    Statutory review time
    up to 2 months after applications close (10 working days for poorly studied territories)
    Result
    The auction results record
  5. Right and contractApproval

    Direct negotiations — instead of an auction

    Without an auction only the national hydrocarbon company can obtain an area — one the Programme reserves for direct negotiations; it applies within 3 years of the area's inclusion. For large fields the national company's share is at least 50 %. After the decision it has 20 working days to pay the bonus and sign.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    2 months for the negotiations from the application (can be extended)
    When it applies
    Only for the national hydrocarbon company
  6. Obligations and reportingWork

    Signature bonus and signing the contract

    The winner pays the signature bonus and submits the signed contract to the Ministry of Energy. If it misses the deadline it loses the right: within 3 working days the contract is offered to the next highest bidder. The starting bonus is set by the Tax Code (from 2,800 MCI for exploration without approved reserves).

    Time limit for the subsoil user
    20 working days from the publication of the auction results
  7. Right and contractWork

    Confidentiality and historical costs agreement

    An agreement with the Geology Committee gives access to the area's geological data and fixes the reimbursement of the state's costs of studying it. The payment obligation arises on the date of the agreement: up to 10,000 MCI is paid by 10 April of the year after production starts; a larger sum in equal quarterly parts over no more than 10 years.

    Who
    The Geology Committee of the Ministry of Industry and Construction
  8. Right and contractEvent

    The exploration and production contract is signed and registered

    The Ministry of Energy registers the contract, which follows the model form; the exploration period, the preparatory period and the production period run from the registration date. On the chart this is month 0.

2

Exploration

Find a pool: seismic, exploration wells, testing

By law
Exploration period up to 6 years (18 for complex projects)
Typically
3.5 years
  1. Project documentsWork

    The exploration project

    A firm licensed to prepare project documents writes the project for the whole exploration period: seismic volumes, the number and depth of wells, testing, studies, timing, protection of the subsoil and the environment. Work is done only under a project with a positive expert conclusion.

    Time limit for the subsoil user
    Within 1 year of the contract registration
  2. EnvironmentApproval

    Notice of the planned activity and screening

    Hydrocarbon exploration and production are subject to mandatory screening. The notice is checked for completeness (2 working days) and published for comments from state bodies and the public. The screening conclusion decides whether an environmental impact assessment is needed; if it is, the scoping conclusion comes with it.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    22 working days from the registration of the notice
  3. Field work and productionWork

    Procurement and contractors

    Goods, works and services are bought under the subsoil users' procurement rules through the register; Kazakh works and services make up at least 70 % of the annual volume (except complex offshore projects). Seismic, drilling, testing and other contractors need a licence for hydrocarbon works and services.

  4. EnvironmentApproval

    Environmental impact assessment of the exploration

    The draft report on possible impacts is published at least 30 calendar days before the public hearings, which are announced at least 20 working days ahead. Comments on the report come within 17 working days and the initiator fixes them within 5; without a signed record of the hearings the conclusion is that the activity is inadmissible.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    30 working days for the assessment conclusion from the registration of the application
    When it applies
    If the screening makes the assessment mandatory
  5. Project documentsApproval

    Review of the exploration project by the central commission

    The central commission, with independent experts, carries out the state review of the basic project documents. Changes and additions to a project are reviewed the same way.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    2 months
    Result
    The expert conclusion
  6. Land and waterApproval

    Public easement over the land for exploration

    Land is not taken for exploration: the akimat, on the subsoil user's application backed by the contract, sets up a public easement. Work may start only after the owners and land users are paid for the easement and compensated for losses under an agreement.

    Who
    The local executive body (akimat)
    Statutory review time
    No separate deadline is set
  7. Obligations and reportingApproval

    Liquidation security: a bank deposit pledge

    Before any operations, for each subsoil area, the liquidation obligations are secured — by a pledge of a bank deposit (a guarantee for contracts signed before the Code and companies at least 50 % owned by the national holding). The documents go to the ministry within 2 working days of the pledge registration.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    7 working days to check the security
    Time limit for the subsoil user
    Before subsoil operations begin
  8. EnvironmentApproval

    Integrated environmental permit

    The Code places hydrocarbon exploration and production in category I, and since 1 January 2025 they need an integrated environmental permit based on best available techniques. The environmental monitoring programme and the waste management programme are part of the permit; the environmental review of the design is done within the permit procedure. The permit has no end date but is revised when BAT requirements change.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working days
  9. Land and waterApproval

    Special water use permit

    Needed to take groundwater or surface water (drilling, the camp) and to discharge treated waste water. The basin water inspectorate issues it, usually for 5 years; for 3 years if the groundwater reserves are not approved.

    Who
    The basin water inspectorate
    Statutory review time
    10 working days
    When it applies
    When water is taken or waste water discharged
  10. Obligations and reportingWork

    Mandatory environmental insurance

    Environmentally hazardous activities on the approved list cannot run without mandatory environmental insurance, which must be in force from the start and throughout.

    Time limit for the subsoil user
    Before the activity starts
  11. Field work and productionWork

    2D/3D seismic and interpretation

    Field acquisition, processing and interpretation: mapping the traps, estimating the resources and choosing the locations of the exploration wells.

  12. Obligations and reportingApproval

    Annual reports on the contract obligations

    The subsoil user reports every year on the work programme, spending, procurement and in-country value. Physical volumes (geophysics, drilling, production) count only when backed by completion certificates, invoices and payment orders; requests for information are answered within 10 working days.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    6 months to analyse the annual report
    Repeats
    Every year
  13. Construction and safetyWork

    Well construction design

    A group or individual technical design: the well structure, drilling fluid, blowout preventers, testing. The requirements are in the industrial safety rules for the oil and gas industry; design documents of hazardous facilities undergo an industrial safety review where the law requires it.

  14. Field work and productionWork

    Drilling exploration wells

    Drilling under the approved project, with coring, well logging and kick control.

  15. EnvironmentApproval

    Permit to flare gas while testing wells

    Flaring raw gas is prohibited except in the cases the Code names. For testing well objects the ministry issues a permit based on the approved project document — for no more than 90 days per object. Applications go through egov.kz / elicense.kz; emergency flaring needs no permit, but the authorities are notified within 10 days.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    8 working days
  16. Field work and productionWork

    Testing the well objects

    Perforation, bringing in the flow, pressure transient tests, sampling oil, gas and water. The results show whether there is a pool worth appraising.

  17. ReservesApproval

    Report on exploration results for a poorly studied territory

    For areas in poorly studied territories a report on form 1-UVG is filed in the first three years of exploration; it is refused if the work programme of the initial exploration period was not fully carried out.

    Who
    The Geology Committee (the authorised body for subsoil study)
    Statutory review time
    1 month
    When it applies
    Only areas in poorly studied territories
  18. ReservesEvent

    A discovery

    A commercial flow is obtained — the subsoil user decides whether to appraise the discovery. For ordinary projects appraisal happens inside the 6-year exploration period; for complex projects the exploration period of up to 18 years is split into stages: search (9 years), appraisal (6 years) and trial production (3 years).

  19. Right and contractApproval

    Extending the exploration period

    The application is filed before the exploration period ends; on extension the blocks outside the new boundaries are removed from the area (the Code sets no fixed share to relinquish). The area can also be reduced voluntarily — that application is also reviewed in 20 working days.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    20 working days
    When it applies
    If exploration is not finished within the main period
3

Appraisal and trial production

Delineate the pool, prove commercial flow and approve the reserves

By law
Within the 6-year exploration period
Typically
2.5 years
  1. Project documentsWork

    Project addendum: appraising the discovery

    Appraisal wells, 3D seismic over the discovery and core and fluid studies are added as a change to the exploration project.

  2. Project documentsApproval

    Review of the addendum by the central commission

    Changes to the exploration project are reviewed like the project itself.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    2 months
  3. Field work and productionWork

    Appraisal wells and studies

    Delineating the pool and refining the net pay, porosity, permeability and saturation, the contacts and the oil and gas properties.

  4. Project documentsWork

    The trial production project

    The wells, rates, volumes, studies and gas utilisation during trial production, which is run to refine the productivity, the fluid properties and the drive mechanism for the reserves estimate.

    Time limit for the subsoil user
    3 months from the subsoil user's decision to run trial production
  5. EnvironmentApproval

    Environmental assessment of trial production

    Trial production is production with new emission sources, so its environmental assessment starts with a new notice of the planned activity and screening; if needed, a full assessment with public hearings follows.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    22 working days for the screening conclusion; a full assessment takes up to 30 more working days
  6. Project documentsApproval

    Review of the trial production project

    Trial production cannot start without a positive conclusion; the gas flaring permits also rest on the project.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    3 months (+ up to 3 months if extended)
  7. EnvironmentApproval

    Integrated permit for trial production

    The new facilities — treatment units, the flare, tanks — are added to the integrated environmental permit before trial production starts, together with the environmental monitoring programme.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working days
  8. Project documentsApproval

    Raw gas processing development programme

    Producing gas (associated gas included) requires an approved programme to process or utilise it; a flaring permit cannot outlast the programme. The programme is updated at least every 3 years and reported on annually.

    Who
    The Ministry of Energy (on the working group's recommendation)
    Statutory review time
    No separate deadline is set
  9. Construction and safetyApproval

    Metering and the crude oil accounting system

    The facilities on the ministry's list are fitted with meters for crude oil, condensate, raw and marketable gas; the data go to the accounting information system. The ministry agrees the metering scheme.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    30 working days to agree the metering scheme
  10. EnvironmentApproval

    Flaring permit for trial production

    Flared volumes must stay within the norms calculated by the approved methodology; the term cannot exceed that of the project document and the gas processing programme.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    2 working days
  11. Field work and productionWork

    Trial production

    Production at the project's volumes with well and reservoir studies. For ordinary projects it runs within the exploration period and may continue in the preparatory period (up to 3 years) with all the oil sold on the domestic market; for complex projects it is a separate stage of up to 3 years.

  12. ReservesWork

    The reserves estimation report

    From the drilling, testing and trial production data the in-place and recoverable reserves of oil, gas and associated components are estimated under the current classification and methodologies.

  13. ReservesApproval

    State review of the reserves

    Until 1 January 2030 hydrocarbon reserves reports are reviewed by the State Commission on Mineral Reserves with independent experts. The approved reserves are the basis of the development project and the move to production.

    Who
    The State Commission on Mineral Reserves (Ministry of Industry and Construction)
    Statutory review time
    The deadline is set by the Commission's regulation (Order No. 171 of 15.05.2024) — check the current version
  14. ReservesEvent

    The reserves on the state balance

    The approved reserves of oil, gas and associated components enter the state balance of mineral reserves.

4

Getting ready to produce

The development project, permits, land, field facilities and the move to the production period

By law
Preparatory period up to 3 years
Typically
2 years
  1. Project documentsWork

    The field development project

    Written for the whole period of profitable production from the reserves that passed the state review: the development scheme, the well stock and pattern, pressure maintenance, production profiles, the mandatory raw gas processing section, subsoil protection. If actual results depart materially from it, the project is revised.

  2. EnvironmentApproval

    Notice of the development and the assessment scope

    Commercial oil production above 500 t a day (gas above 500 thousand m³) requires a full assessment without screening: the notice leads straight to the scoping conclusion. Smaller production goes through screening, as in exploration.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    22 working days from the registration of the notice
  3. Land and waterApproval

    Heritage survey before the land is allocated

    Before land plots are allocated an archaeological survey is carried out at the developer's cost; it ends with a heritage expertise conclusion by a licensed expert under a contract. A copy goes to the akimat within 5 working days; finds lead to excavation or a change of design.

    Who
    A licensed expert under contract; a copy to the akimat
    Statutory review time
    up to 30 calendar days (the exact term is set by the contract)
  4. EnvironmentWork

    Impact report and public hearings

    The initiator prepares the impact report, publishes the draft and holds the hearings at its own cost, agreeing the place and time with the akimat. The announcement is in Kazakh and Russian, in at least one newspaper and on one TV or radio channel; written comments are accepted until 3 working days before the hearings.

    Time limit for the subsoil user
    The draft report stays public for at least 30 calendar days; the announcement comes at least 20 working days before the hearings
  5. Construction and safetyApproval

    Design inputs: the planning brief and utility conditions

    The architectural planning brief and the technical conditions for utility connections are the inputs to the construction design; they are obtained through elicense.kz / egov.kz.

    Who
    The akimat's architecture and planning body; utility owners
    Statutory review time
    Until 1 July 2026 — 6 working days for technically simple objects; check the deadlines under the rules of the new Construction Code
  6. Land and waterApproval

    Land for the production facilities: a lease for the contract term

    For production and the field facilities the subsoil user gets temporary paid land use (a lease) for the whole contract term. It applies to the akimat with a copy of the contract; the land commission prepares its opinion, then the decision is taken and the lease signed.

    Who
    The local executive body (akimat)
    Statutory review time
    up to 15 working days (not counting the land management project)
  7. Construction and safetyWork

    Field facilities design

    Gathering and treating oil, gas and water, the pressure maintenance system, pipelines, power supply, roads, the camp. The design documents of a hazardous production facility undergo an industrial safety review and are agreed with the state industrial safety inspector.

  8. EnvironmentApproval

    Environmental impact assessment conclusion

    The conclusion that the activity is admissible; its conditions carry into the design and the environmental permit. It has no expiry date, but a material change of the activity needs a new assessment.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    30 working days from the registration of the application
  9. Land and waterApproval

    Changing the designated use of the land

    Needed when the plot's designated use does not allow field facilities. The application with the cadastral number goes to the akimat, which reports the result.

    Who
    The local executive body (akimat)
    Statutory review time
    up to 16 working days outside settlements (up to 8 inside them)
    When it applies
    If the plot's designated use does not fit the facilities
  10. Project documentsApproval

    Review of the development project

    A positive conclusion is a condition for moving to the production period: the contract's production volumes and timing follow the approved project.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    3 months (+ up to 3 months if extended)
  11. EnvironmentApproval

    Sanitary protection zone: the sanitary conclusion

    The design of the field's sanitary protection zone and emission limits undergoes a sanitary review within the construction design review; the conclusion on the zone project is issued by the Sanitary and Epidemiological Control Committee through egov.kz.

    Who
    The Sanitary and Epidemiological Control Committee of the Ministry of Health
    Statutory review time
    10 working days
  12. Land and waterApproval

    Water use at the field

    A special water use permit covers water intake and discharges of treated waste water; injecting formation water produced with the oil to maintain reservoir pressure needs none. Work affecting water bodies and water protection zones is agreed with the basin inspectorate.

    Who
    The basin water inspectorate
    Statutory review time
    10 working days
  13. EnvironmentApproval

    Integrated permit for the production facilities

    The new facilities — oil and gas treatment, water injection, tank farms — start up only with an integrated environmental permit; the main sources of category I facilities run an automated emission monitoring system that reports in real time.

    Who
    Ministry of Ecology and Natural Resources (the environmental authority)
    Statutory review time
    The Code sets no single deadline: the procedure has stages (completeness — 5 working days, opinions of state bodies — 25, the draft permit — 10, etc.); run in sequence they come to about 60 working days
  14. Construction and safetyApproval

    Comprehensive non-departmental design review

    Construction designs undergo a comprehensive non-departmental review. For objects of the first and second responsibility levels — most field facilities — it is a state monopoly carried out by the state expert organisation.

    Who
    The state expert organisation
    Statutory review time
    Under the rules in force until 1 July 2026 — 15 to 45 working days by complexity; check the deadlines under the new rules
  15. Construction and safetyApproval

    Industrial safety of the design

    The design of a hazardous facility undergoes an industrial safety review by an accredited firm and is agreed with the chief state industrial safety inspector (national for facilities in several regions, regional for one). Changes to the design are agreed again.

    Who
    An accredited expert firm; the state industrial safety inspector (Ministry of Emergency Situations)
    Statutory review time
    No separate deadline is set
  16. Construction and safetyEvent

    Notice of the start of construction

    Construction starts after the state architectural and construction control bodies are notified through elicense.kz, with the positive expert conclusion attached. It is a notification, not a permit.

  17. Construction and safetyApproval

    Industrial safety declaration

    For hazardous facilities subject to declaration the operator writes the declaration — for facilities being designed and in operation; the authorised body registers it. The facility cannot operate without a registered declaration; after changes affecting safety it is reissued within 3 months.

    Who
    The industrial safety authority (Ministry of Emergency Situations)
    Statutory review time
    No separate deadline is set
  18. Construction and safetyWork

    Building the facilities and drilling producers

    Construction runs under the owner's technical supervision and the designer's author supervision. During the preparatory period oil may be produced at trial production volumes and sold on the domestic market.

  19. Right and contractApproval

    Moving to the production period

    The production period starts with the registration of an addendum to the exploration and production contract (or a production contract). The conditions: reserves that passed the state review and a development project with a positive conclusion. The production period is up to 25 years, up to 45 for large fields (over 100 Mt of oil or 50 bcm of gas).

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    20 working days to consider the contract change
  20. Construction and safetyWork

    Emergency plan, rescue service, insurance

    The emergency response plan is agreed with a professional rescue service (then every year by 1 December); an own or contracted service covers the facility. Before operation starts the owner of a hazardous facility takes out mandatory liability insurance — for no more than 12 months, then renewed.

    Time limit for the subsoil user
    Insurance — before operation starts
  21. Construction and safetyWork

    Acceptance of the facilities into operation

    The owner, with the general contractor, technical supervision and author supervision, collects the declaration of conformity and the conclusions on work quality, fire safety and conformity to the design, and signs the acceptance certificate. Then the rights to the new facilities are registered.

    Time limit for the subsoil user
    The contractors hand over the readiness documents within 3 working days of the owner's request
  22. Field work and productionEvent

    Production starts under the development project

    The production period is registered, the facilities accepted and the permits obtained — the field moves to commercial production.

5

Production

Development under the project, monitoring, reporting and contract obligations

By law
Production period up to 25 years (45 for large fields)
Typically
25 years
  1. Obligations and reportingWork

    Financial security for closing category I facilities

    The operator of a category I facility provides the state with financial security for closing it down: a guarantee, a deposit or property pledge, insurance. The bank deposit share must reach at least 50 % 10 years after commissioning and 100 % after 20 years. The security does not remove the duty to do the closure itself.

    Time limit for the subsoil user
    Within 3 years of commissioning
  2. Field work and productionWork

    Production under the development project

    Drilling and bringing wells on, pressure maintenance, well and reservoir surveillance, development control under the Unified Rules; daily and monthly reports on oil, gas and condensate.

  3. Obligations and reportingWork

    Procurement and in-country value

    Procurement follows the subsoil users' rules through the register of goods, works and services; Kazakh works and services are at least 70 % a year (except complex offshore projects); in-country value is reported on the approved forms.

    Repeats
    Every year
  4. Obligations and reportingWork

    The subsoil user's taxes and payments

    Mineral extraction tax, export rent tax and export duty, excess profit tax, corporate income tax, property tax and the historical costs payment — under the 2026 Tax Code (details in the tax section).

    Repeats
    Monthly, quarterly and yearly
  5. EnvironmentApproval

    Permit for technologically unavoidable flaring

    Start-ups, commissioning, repairs — flaring under a permit within the norms; emergency flaring — without a permit, notifying the authorities within 10 days. The raw gas processing programme is updated at least every 3 years and reported on annually.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    2 working days
    Repeats
    As needed
  6. Construction and safetyWork

    Industrial safety in operation

    The emergency response plan — every year to the rescue service by 1 December; registration of hazardous facilities and equipment; industrial safety reviews of equipment, buildings and structures; annual renewal of the liability insurance; reissuing the declaration within 3 months of changes.

    Repeats
    Every year
  7. EnvironmentWork

    Environmental monitoring in operation

    Monitoring under the programme that is part of the environmental permit; electronic reports to the National environmental data bank; automated emission monitoring on the main sources; waste managed under the programme. Breaches found in monitoring are reported within 3 working days.

    Repeats
    Continuous; reports periodically
  8. Obligations and reportingWork

    Training, R&D and regional development — 1 % each

    From the second year of production (the first under the new model contract) the subsoil user funds, every year, the training of Kazakh staff (1 % of last year's production costs), R&D (1 % of production costs — paid into the budget by 31 March of the next year) and the region's socio-economic development (1 % of the contract investments).

    Repeats
    Every year
  9. Obligations and reportingApproval

    Annual contract reports — the ministry's analysis

    The ministry checks the report against the work programme, the 1 % obligations, procurement and in-country value; if it finds a breach it sends a notice of breach of the contract terms.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    6 months to analyse the annual report
    Repeats
    Every year
  10. Project documentsApproval

    Author supervision and development analysis

    The design firm supervises how the development project is carried out; a development analysis is prepared as often as the Unified Rules require and reviewed by the central commission.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    3 months (+ up to 3 months if extended)
    Repeats
    Periodically, under the Unified Rules
  11. Project documentsApproval

    A new development project or an addendum

    The project is revised when actual results depart materially from it, reserves grow or the development scheme changes. The new document goes through the central commission like the first one.

    Who
    The Central Commission for Exploration and Development of Hydrocarbon Fields
    Statutory review time
    3 months (+ up to 3 months if extended)
    When it applies
    When results depart materially from the project or reserves change
  12. ReservesApproval

    Re-estimating the reserves

    With new drilling and production data the reserves are re-estimated and the report goes through the state review again; the changes enter the state balance.

    Who
    The State Commission on Mineral Reserves
    Statutory review time
    The deadline is set by the Commission's regulation (Order No. 171 of 15.05.2024) — check the current version
    When it applies
    When reserves grow or change materially
  13. Right and contractApproval

    Extending the production period

    The application is filed at least a month before the production period ends (for large fields at least 6 months before the contract expires). If the contract does not match the current model contract, a new production contract on the model form is signed.

    Who
    Ministry of Energy (the competent body)
    Statutory review time
    2 months
    When it applies
    If production stays profitable beyond the period
  14. Right and contractEvent

    The subsoil use right ends

    The right ends when the contract expires, when the subsoil user gives it up or on other grounds of the Code. The liquidation and geological report deadlines run from this date.

6

Liquidation and return of the area

Abandon the wells and facilities, reclaim the land, return the area to the state

By law
Start within 6 months of the right ending
Typically
3 years
  1. LiquidationWork

    The liquidation project

    The project to liquidate the consequences of subsoil use — wells, pipelines, tanks, pits, cuttings storage, land reclamation — is usually prepared in advance. The liquidation design of a hazardous facility undergoes an industrial safety review and is agreed with the state inspector.

    Time limit for the subsoil user
    Submitted for review within 2 months of the right ending
  2. ReservesWork

    The final geological report

    The report goes to the Geology Committee in three paper copies and electronically — for the national and territorial geological funds and the subsoil user.

    Time limit for the subsoil user
    Within 3 months of the contract ending
  3. LiquidationEvent

    Notice of the start of works — 15 calendar days ahead

    A notice with the justification, data on the remaining reserves and waste and the reviewed project goes to the Ministry of Energy. Works must start within 6 months of the right ending; the ministry may extend this if starting is impossible for reasons beyond the user's control.

    Time limit for the subsoil user
    Start the liquidation within 6 months of the right ending
  4. LiquidationWork

    Abandoning the wells and facilities

    Well abandonment by a licensed contractor (well suspension and abandonment is a sub-type of the hydrocarbon works licence), removal of equipment and pipelines, closing pits and cuttings storage, removing waste.

  5. Land and waterWork

    Reclaiming the disturbed land

    After the removal of equipment the land is restored under the liquidation plan: the stripped and stored topsoil is put back and the plots are made fit for further use.

  6. LiquidationWork

    Notices that the works are finished

    The Ministry of Energy and the local executive body are told that the liquidation is complete.

    Time limit for the subsoil user
    The ministry within 15 calendar days, the akimat within 30
  7. LiquidationApproval

    Acceptance by a commission and the liquidation act

    The commission inspects the area; the act is signed by the subsoil user, the Ministry of Energy and the environmental, industrial safety, sanitary and geology bodies, and by the land user. Liquidation is complete from the day the act is signed.

    Who
    A Ministry of Energy commission with the environmental, industrial safety, sanitary and geology bodies
    Statutory review time
    10 working days after inspecting the area
  8. Land and waterApproval

    Returning the land

    The land leases and easements end; the reclaimed plots go back to the owner or to the reserve lands.

    Who
    The local executive body (akimat)
    Statutory review time
    No separate deadline is set
  9. Right and contractEvent

    The subsoil area is back with the state

    With the liquidation act signed, the obligations for the area are fulfilled: the area returns to the state subsoil fund and the liquidation security is no longer needed.

How to read this map

  • The scenario is typical: an onshore oil field and an exploration and production contract won at an auction. The durations of the work are guides from practice; the law sets maximum periods and the deadlines of state bodies, which are shown separately.
  • Offshore and complex projects, gas and gas-condensate fields, production-only contracts and areas in poorly studied territories have their own features — the step descriptions mention them, but the chart does not show them.
  • Working days exclude weekends and public holidays. A state body's deadline usually runs from the day a complete set of documents is filed; a return for revision starts it again.

Legislation as of September 2026. Reference material, not legal advice: check the current versions of the acts before making decisions.