On approval of the Rules for conservation and liquidation in the exploration and production of hydrocarbons
The English title is an unofficial translation.
Set the procedure for conserving (temporarily suspending) a subsoil area and liquidating the consequences of hydrocarbon exploration and production, including notice to the competent body, the required conservation/liquidation project and acceptance of completed works by a commission.
What matters for an oil & gas company
- 15 calendar days before starting, the subsoil user notifies the competent body (Ministry of Energy), attaching a justification, data on remaining reserves and wastes, and an approved project that has passed the required expert reviews.
- Completion is reported within 15 calendar days, and to the regional akimat within 30 calendar days after liquidation; a commission signs the conservation/liquidation act within 10 working days after inspecting the site.
- Cover conservation of the subsoil area and liquidation of wells, pipelines, tanks, oil pits, sludge collectors and other facilities.
The summaries are for orientation and are not legal advice. Only the official text is legally binding. Checked in September 2026.