Construction project expertise rules
On approval of the Rules for comprehensive non-departmental expertise of construction projects for new buildings and structures, their complexes and engineering and transport utilities, and for changes (reconstruction, expansion, technical re-equipment, modernisation and major repair) to existing ones
The English title is an unofficial translation.
2026 rules under the Construction Code (in force from 1 July 2026, replacing the 2015 rules) on how projects for building new, or changing existing, buildings, structures and utilities pass comprehensive non-departmental expertise: filing through the one-stop portal, completeness check, review terms and extensions, expert opinions, expertise of unfinished and unauthorised construction, and expert support.
What matters for an oil & gas company
- The project, with its source materials and permit documents, is filed through the one-stop portal for organising project development and expertise (except classified and 'for official use' projects). Completeness is checked within 2 working days by the state expert organisation for projects whose expertise is a state monopoly (Art. 104 sub-item 2) of the Code), within 5 working days by the operator of the non-state digital system for projects reviewed by expert organisations (Art. 109(1)), and within 5 working days for classified and 'for official use' projects (paras 12, 12-1).
- The review takes no more than 45 working days for objects of responsibility levels I and II and for unfinished or unauthorised construction, 30 for level III, 60 for objects of national or interstate significance and unique objects, and 15 for certain estimate corrections (para 28). Only the 45-day term may be extended, by 15 working days at the customer's request, for unique objects and objects of national or interstate significance (paras 29–30).
- Where the expertise is not a state monopoly and the project is not a public procurement item, the customer chooses any expert organisation (para 10); the expertise is done under a contract and its cost is included in the project development cost (para 14).
- Objects listed in Art. 98(4) of the Code and feasibility studies are not subject to this expertise (para 4); design and estimate documentation counts as complete once it has a positive expert opinion and is approved (para 6).
The summaries are for orientation and are not legal advice. Only the official text is legally binding. Checked in November 2026.