Quick refresher
- The order of the steps: data checks and depth matching → zonation (dividing the section into beds by lithology, reservoirs and fluids) → shale volume → porosity → formation water resistivity → saturation → cut-offs and net thickness → averaging → uncertainty.
- Each step uses the previous ones: effective porosity needs shale volume, from a water-bearing bed needs the porosity of that bed, saturation needs porosity, and , and net thickness needs all of them together.
- Formation water resistivity is a single number per interval. We check it in several ways. The model with the adopted parameters must give in water-bearing beds.
- High resistivity does not by itself mean oil: tight rocks are also highly resistive. A productive bed must pass the cut-offs for shale volume, porosity and saturation at the same time.
- We average porosity over thickness and water saturation over pore volume. The main result for the estimate of hydrocarbons in place is the hydrocarbon pore thickness .
- Marginal beds (beds close to the cut-off limits) change the result most. The choice of the saturation model, of the shale-volume relationship and of the cut-offs can include them or exclude them entirely.
effective porosity of a shaly bed from density
water resistivity from a clean water-bearing bed
Archie's equation for clean beds
hydrocarbon pore thickness over the beds that pass the cut-offs
how a relative error in saturation leads to an error in the pore thickness of a bed
- Starting the calculation without checking the data and the depth matching of the runs.
- Taking a highly resistive tight streak for a productive one without looking at porosity.
- Taking from a shaly water-bearing bed, or not bringing it to formation temperature.
- Choosing the saturation model or the shale volume to suit the desired result.
- Averaging water saturation over thickness instead of over pore volume.
- Reporting a single number for net thickness, with no alternatives, when a marginal bed changes it by a third.
After this lesson you can
- list the interpretation steps in order and explain which results each step takes from the previous ones
- name, for each step, the main method, the main check and the lesson where it is covered in detail
- divide the section into beds by lithology, permeability and fluid, and find the oil–water contact (the surface below which the rock holds water instead of oil)
- make a quick-look interpretation of several beds: shale volume, porosity, water resistivity, water saturation
- apply cut-offs (limit values that separate reservoir from non-reservoir rock) and find the net thickness and the net pay, the net-to-gross ratio, the average parameters and the hydrocarbon pore thickness
- assess which decisions change the result most, and present it together with a range
The interpretation map: the steps and their order
Interpretation answers four questions: what the section is made of, where the reservoirs are, what is in them, and how much there is. We answer them step by step, and the dependencies set the order of the steps. The effective porosity of a shaly bed needs the shale volume. The water resistivity from a water-bearing bed needs the porosity of that bed. The water saturation needs the porosity, the water resistivity and the true resistivity of the formation. So an error at any step flows down the chain, and we place checks between the steps, not only at the end.
A vertical diagram of nine blocks from top to bottom: 0 — data checks and depth matching; 1 — zonation: lithology, reservoirs, fluids; 2 — shale volume; 3 — porosity; 4 — formation water resistivity; 5 — saturation; 6 — cut-offs and net thickness; 7 — averaging and hydrocarbon pore thickness; 8 — uncertainty and conclusion. The blocks are joined by arrows pointing down. To the right of blocks 2 to 5 a feedback arrow runs from saturation to water resistivity and shale volume, labelled “check: water-bearing beds give S_w of about 1”. To the left of blocks 2 to 6 is a band labelled “core and tests”.
- Step
- 0. Data and depths
- Question
- can the curves be trusted; do the runs agree in depth
- Step
- 1. Zonation
- Question
- where the shales, reservoirs and non-reservoir rocks are; which fluids; where the contacts are
- Details
- Gamma ray log and natural gamma ray spectrometry, Spontaneous potential (SP) log, Resistivity logs: electrical and induction tools, Microresistivity tools and flushed-zone resistivity, Lithology and porosity from crossplots, Lithology from the photoelectric factor and spectral gamma ray, M–N and MID plots for complex lithologies
- Step
- 2. Shale volume
- Question
- what share of the volume is occupied by shale
- Details
- Determining shale volume
- Step
- 3. Porosity
- Question
- how many pores there are — total and effective porosity
- Step
- 4. Water resistivity
- Question
- at formation temperature
- Step
- 5. Saturation
- Question
- what share of the pores is occupied by water; whether the oil is moveable
- Step
- 6. Cut-offs
- Question
- what to count as reservoir and as productive
- Step
- 7. Averaging
- Question
- net thickness, average parameters, hydrocarbon pore thickness
- Details
- averaging
- Step
- 8. Uncertainty
- Question
- how reliable the result is and what changes it
In manual interpretation we do many of the steps with charts: graphs for borehole corrections, porosity, lithology and saturation. The topic Interpretation charts: how to read them shows how to read them and where they go wrong.
We can interpret in two ways. In bed-by-bed interpretation, we divide the section into beds, take the characteristic readings opposite each bed, and calculate the properties of the bed. This is how we do a quick-look. It is also how the traditional report on the results of well logging is organised. For each bed it gives the interval, the thickness, the properties and the fluid type: oil, gas, water or “unclear”. In sample-by-sample interpretation, a program calculates the properties at every recording depth and then sums the intervals that pass the cut-offs. The sample-by-sample approach shows changes within a bed better. The bed-by-bed approach is clearer and easier to check. The steps are the same in both, and in this lesson the quick-look goes bed by bed.
Steps 0–1: data checks and zonation
Before calculating, we check the data: the heading, the calibrations and the repeat section, the logging speed, the quality indicators of the methods, and the depth matching of the runs (checklist). Then we check the borehole: the caliper log against the bit, the type of mud, and the expected invasion profile (first checks). We mark unreliable intervals at once. In washouts the density and the neutron porosity are distorted, so we evaluate such a bed by other methods or exclude it.
Then we divide the section into beds. This step is qualitative (it uses no calculations), but everything that follows depends on it: each bed gets its own readings and its own parameters.
- Lithology. We recognise shales by a high gamma ray (GR) and by the spontaneous potential (SP) at the shale baseline, the line that the SP follows opposite shales (Gamma ray log and natural gamma ray spectrometry, Spontaneous potential (SP) log). We recognise sandstones, limestones, dolomites and evaporites (such as salt and anhydrite) by density, the photoelectric factor and the crossplots of the porosity methods (Lithology and porosity from crossplots, Lithology from the photoelectric factor and spectral gamma ray). We place bed boundaries at the middle of the transition of the curves.
- Reservoirs. The direct signs of permeability are mudcake on the caliper log (a diameter smaller than the bit), separation of resistivity curves of different depths of investigation, and positive microlog separation on the microresistivity tools (more). An indirect sign is the deflection of the SP from the shale baseline. High density with a low GR and coincident resistivity curves indicate a tight streak (a thin bed with very little pore space).
- Fluids. We compare beds of the same lithology and porosity by their deep resistivity: hydrocarbons raise it many times over (Resistivity logs: electrical and induction tools). With fresh mud, the ratio of the flushed-zone resistivity to the true resistivity, , is close to in a water-bearing bed. In an oil-bearing bed it is much lower (resistivity profile). The crossover of the neutron and density curves shows gas (more). The oil–water contact (OWC) shows up as a drop in resistivity within one clean bed. The drop is abrupt, or gradual if there is a capillary transition zone above the contact (Capillary pressure and the transition zone).
From here on, we carry out all the steps on one assumed vertical well. The lesson Log acquisition, processing and presentation covers its heading and runs. The formation temperature is about 80 °C, the mud is fresh, and the filtrate resistivity at formation temperature is = 0.191 Ω·m. The density run is tied to the resistivity run by the GR, and the neutron curve is recorded in sandstone units.
Six narrow vertical tracks and a depth column from 2598 to 2636 metres, with the letters of the beds A, B, C, D, G, E1, E2, F on the left. GR: about 102 API in the shales, 22–29 API in sandstones B, C, E1, E2, 58 API in bed D, 83 API in bed G. Resistivities on a logarithmic scale: the deep tool about 31 Ω·m in B, 56 Ω·m in the tight streak C, about 10 Ω·m in D, 14 Ω·m in E1 and 1.6 Ω·m in the water-bearing E2; the microresistivity tool 4.7–7.9 Ω·m in the permeable sandstones. The result tracks are steps by bed: shale volume with a cut-off line at 0.35 (exceeded by the shales and bed G), effective porosity with a cut-off line at 0.10 (below it are C and G), water saturation with a cut-off line at 0.50 (0.195 in B, 0.44 in D, 0.344 in E1, 1 in E2). On the right are the flags: reservoir — B, D, E1, E2; productive bed — B, D and E1 above the contact at 2621 metres.
- Bed
- A
- Interval, m
- 2600.0–2606.0
- GR, API
- 102
- , g/cm³ /
- 2.550 / 0.330
- / , Ω·m
- 3.2 / 3.2
- Bed
- B
- Interval, m
- 2606.0–2612.0
- GR, API
- 27
- , g/cm³ /
- 2.261 / 0.244
- / , Ω·m
- 30.6 / 5.5
- Bed
- C
- Interval, m
- 2612.0–2613.2
- GR, API
- 29
- , g/cm³ /
- 2.567 / 0.061
- / , Ω·m
- 56.3 / 52
- Bed
- D
- Interval, m
- 2613.2–2617.0
- GR, API
- 58
- , g/cm³ /
- 2.380 / 0.242
- / , Ω·m
- 9.58 / 7.2
- Bed
- G
- Interval, m
- 2617.0–2618.6
- GR, API
- 83
- , g/cm³ /
- 2.505 / 0.255
- / , Ω·m
- 4.3 / 4.3
- Bed
- E1
- Interval, m
- 2618.6–2621.0
- GR, API
- 25
- , g/cm³ /
- 2.325 / 0.203
- / , Ω·m
- 14 / 7.9
- Bed
- E2
- Interval, m
- 2621.0–2629.0
- GR, API
- 22
- , g/cm³ /
- 2.318 / 0.201
- / , Ω·m
- 1.58 / 4.7
- Bed
- F
- Interval, m
- 2629.0–2635.0
- GR, API
- 102
- , g/cm³ /
- 2.550 / 0.330
- / , Ω·m
- 3.2 / 3.2
| Bed | Interval, m | GR, API | , g/cm³ / | / , Ω·m |
|---|---|---|---|---|
| A | 2600.0–2606.0 | 102 | 2.550 / 0.330 | 3.2 / 3.2 |
| B | 2606.0–2612.0 | 27 | 2.261 / 0.244 | 30.6 / 5.5 |
| C | 2612.0–2613.2 | 29 | 2.567 / 0.061 | 56.3 / 52 |
| D | 2613.2–2617.0 | 58 | 2.380 / 0.242 | 9.58 / 7.2 |
| G | 2617.0–2618.6 | 83 | 2.505 / 0.255 | 4.3 / 4.3 |
| E1 | 2618.6–2621.0 | 25 | 2.325 / 0.203 | 14 / 7.9 |
| E2 | 2621.0–2629.0 | 22 | 2.318 / 0.201 | 1.58 / 4.7 |
| F | 2629.0–2635.0 | 102 | 2.550 / 0.330 | 3.2 / 3.2 |
Neutron porosity is in sandstone units; is the deep tool after corrections; is the microresistivity tool corrected for mudcake; the resistivities are at formation temperature. Caliper: 210–211 mm opposite sandstones B, D, E1 and E2 (mudcake, with a 215.9 mm bit), 216 mm opposite streak C, 228–236 mm opposite the shales (washouts).
- Bed
- A, F
- Rock
- shale: high GR, washouts
- Reservoir
- no
- Fluid
- —
- Bed
- B
- Rock
- clean sandstone
- Reservoir
- yes: mudcake, and differ
- Fluid
- oil: is 19 times higher than in E2
- Bed
- C
- Rock
- tight (cemented) sandstone: low GR, high density
- Reservoir
- no: no mudcake,
- Fluid
- —; the high is due to low porosity
- Bed
- D
- Rock
- shaly sandstone: GR 58 API
- Reservoir
- yes: mudcake
- Fluid
- probably oil: 9.58 Ω·m
- Bed
- G
- Rock
- silty shale
- Reservoir
- no
- Fluid
- —
- Bed
- E1
- Rock
- clean sandstone
- Reservoir
- yes
- Fluid
- oil
- Bed
- E2
- Rock
- clean sandstone
- Reservoir
- yes
- Fluid
- water: the microresistivity tool reads three times higher than the deep tool
| Bed | Rock | Reservoir | Fluid |
|---|---|---|---|
| A, F | shale: high GR, washouts | no | — |
| B | clean sandstone | yes: mudcake, and differ | oil: is 19 times higher than in E2 |
| C | tight (cemented) sandstone: low GR, high density | no: no mudcake, | —; the high is due to low porosity |
| D | shaly sandstone: GR 58 API | yes: mudcake | probably oil: 9.58 Ω·m |
| G | silty shale | no | — |
| E1 | clean sandstone | yes | oil |
| E2 | clean sandstone | yes | water: the microresistivity tool reads three times higher than the deep tool |
The OWC is at 2621.0 m: in one and the same clean sandstone falls from 14.0 to 1.58 Ω·m. There is no gas: on scales compatible with sandstone the neutron and density curves do not cross over in the sandstones.
Steps 2–3: shale volume and porosity
We determine shale volume before porosity. We need it to correct the porosity of shaly beds and to choose the saturation model. The main method is the gamma ray index, which shows how far the GR reading lies between the clean-formation baseline and the shale baseline of the same sequence. We use it with a relationship checked against core (Determining shale volume). We check the result with other indicators: the SP and the difference between neutron and density porosity (more). We draw the shale baseline through thick, uniform shales, not through the peak of a highly radioactive streak.
In a sand–shale (siliciclastic) section we most often take porosity from the density log, using the matrix density (the density of the rock grains) from the lithology and the filtrate density (Porosity from the density log). In a shaly bed we subtract the contribution of the shale. This gives the effective porosity (shale correction). The neutron and sonic logs serve as checks (Porosity from the neutron log, Porosity from the sonic log). In mixed lithology we find porosity and composition from crossplots (Lithology and porosity from crossplots). In gas-bearing beds we use the density–neutron pair with a gas correction (Gas, shale, carbonate and pressure effects on porosity logs). Nuclear magnetic resonance (NMR) logging divides the pore space into bound and free water (Nuclear magnetic resonance (NMR) logging).
- GR baselines
- clean rock 22 API (bed E2), shale 102 API (beds A and F, excluding the highly radioactive streak)
- Relationship
- Larionov relationship for older rocks (a standard shale-volume relationship), (adopted from the core of the field; assumed)
- Densities
- matrix (quartz) 2.65, filtrate 1.00, shale 2.55 g/cm³; neutron porosity in shale 0.33
- Readings
- the table above
- Density “porosity” of shale: .
- Bed B: , ; ; .
- Bed C: , , — tight.
- Bed D: , ; ; . Neutron check: — it agrees with the GR estimate.
- Bed G: , . Beds E1 and E2: and 0, and 0.201.
What it means. Two independent indicators of the shale volume of bed D agree (0.289 from the GR and 0.290 from the neutron and density). This means that we chose the baselines and the relationship sensibly. A linear estimate would give a shale volume of 0.450 in D; this will be useful at the uncertainty step. The shale correction reduced the porosity of D by 0.018, and the porosity of the clean beds by only thousandths. Residual oil (oil that the filtrate leaves behind) in the flushed zone lowers the density slightly and overestimates . Here this effect is below 0.01, so we ignore it. The data in this example are assumed for illustration.
Step 4: formation water resistivity
is a single number for the whole interval that contains one water, and all the saturations depend on it (more). We take it at formation temperature and check it in several ways. The ways are water samples taken in tests, the SP, the apparent water resistivity (the water resistivity calculated from the resistivity and porosity of a clean water-bearing bed), and the Pickett plot (a log–log plot of resistivity against porosity) (Determining formation water resistivity, from the SP, Resistivity–porosity crossplots). needs the porosity of the water-bearing bed, which is why this step comes after porosity. The bed itself must be clean and thick, because in shaly beds comes out too low.
- Bed E2
- clean, below the contact: = 0.201, = 1.58 Ω·m
- Coefficients
- ,
- Water sample of the same horizon from a neighbouring well
- 0.146 Ω·m at 25 °C
- Formation temperature and filtrate
- 80.3 °C, = 0.191 Ω·m (lesson Log acquisition, processing and presentation)
- Ω·m. We take it as .
- We bring the sample to formation temperature with the Arps formula: Ω·m. This is 4.5% higher, and the discrepancy is within the accuracy of the methods.
- The contrast between filtrate and water is . In bed E2, , as it should be in a water-bearing bed. In bed B, , which is 17 times smaller: a sign of oil.
What it means. The check “ in a water-bearing bed” tells us nothing for E2 itself, because we took from E2. The independent checks are the water sample and the ratio of the flushed-zone and formation resistivities. If the sample had differed from by several times, we would have looked for the cause, not averaged the two values (reconciling the estimates). The data in this example are assumed for illustration.
Step 5: saturation
We calculate saturation from the true formation resistivity , the porosity and . is the deep tool reading after corrections for the borehole, the enclosing rocks (the beds above and below) and invasion (how to find it). In clean beds Archie's equation works, with coefficients from core (Archie's equation and saturation of clean reservoirs). In shaly beds the clays conduct current, and Archie's equation overestimates water saturation. There we need a shaly-sand model. We choose it according to the form of the shale distribution (how the shale is spread in the rock), and we check it on water-bearing shaly beds (Water saturation in shaly sands). We choose the model before the calculation, not by which result we like better.
The flushed-zone resistivity gives a second saturation, , and with it a check of oil moveability. If is noticeably larger than , the filtrate has displaced some of the oil, which means that the oil is moveable (more).
- Parameters
- = 0.0638 Ω·m, ,
- Shales
- = 3.2 Ω·m (thick shales A and F)
- Model
- Archie at ; at higher shale volume, Simandoux (a shaly-sand model) in its common form (models)
- Porosity and shale volume
- from the previous example
- Bed B (Archie): .
- Bed E1: . There is more water at the contact than in B.
- Bed D (at , Simandoux gives a quadratic equation, ): , , ; .
- For comparison, Archie in bed D gives , which is higher by 0.119. Archie attributes the conductivity of the clays to water.
- Bed C by Archie: . A number comes out, but in a tight rock with = 0.047 it means nothing.
- Moveable oil in B: , hence . The filtrate has displaced most of the oil.
What it means. In nearly clean beds the models differ little. Simandoux would give 0.190 in bed B instead of 0.195, so here Archie overestimates the water saturation only slightly. Bed D is marginal. By the shaly-sand model its water saturation is 0.440, and by Archie it is 0.559. With a cut-off of 0.50, the bed is productive in the first case and not in the second. Core data decide which model is right: the water saturation of samples cut with oil-based mud, and the cation exchange capacity of the clays (their ability to hold exchangeable ions). A test of bed D decides it too. A wish to show more hydrocarbons in place does not. The data in this example are assumed for illustration.
Steps 6–7: cut-offs, net thickness, averaging
Cut-offs (in Russian-language reserves estimation also called “conditional limits”, from the Russian konditsionnye predely) divide the section. Shale volume and porosity cut-offs separate reservoir from non-reservoir rock. A water saturation cut-off separates productive reservoir from water-bearing reservoir (more). We apply the cut-offs in sequence, and each level gives its own thickness. The gross thickness is the whole bed from top to base. The net thickness is the sum of the reservoir intervals. The net pay is the reservoir with hydrocarbons above the contact. The cut-offs themselves are a decision, not a property of the rock. The advanced section covers where they come from.
Then we average the parameters over the same intervals for which we determined the thickness: porosity over thickness, and water saturation over pore volume. The result for the estimate of hydrocarbons in place is the hydrocarbon pore thickness . This is the thickness of the layer of hydrocarbons that we would get if we gathered them out of the pores (more). We present the result as a table by bed and a summary for the unit. In the logging report we give each bed a fluid type and recommendations: which intervals to test and perforate.
- Field cut-offs (assumed)
- , ,
- Unit
- the sequence from the top of bed B (2606.0 m) to the base of E2 (2629.0 m); OWC 2621.0 m
- Bed properties
- from the previous examples
- Reservoir (by shale volume and porosity): B, D, E1, E2. C ( = 0.047) and G ( = 0.626) did not pass. The net thickness is m, against a gross thickness of 23.0 m. So the net-to-gross ratio is .
- Productive reservoir (above the OWC and ): B, D, E1. The net pay is 12.2 m.
- Average porosity over thickness: pore thickness m, and .
- Average water saturation over pore volume: m, and .
- Hydrocarbon pore thickness by bed: B m, D 0.311 m, E1 0.309 m. In total m. The same result comes from .
What it means. Under every square metre of area at the well there are about 1.75 m³ of oil at reservoir conditions. Bed B gives 65% of this pore thickness. The marginal bed D gives 18%, although in thickness it is almost a third of the productive section. Bed E2 is included in the net thickness but not in the net pay, because it is a water-bearing reservoir. That is why the NTG here refers to the whole penetrated interval, including the water-bearing part below the OWC. For the gross rock volume above the contact, we apply a fraction calculated only for the interval above the contact; in this example it is smaller. If the estimate of hydrocarbons in place takes the NTG for the reservoir, we must take the averages for the reservoir too. We must not mix the levels (why). The data in this example are assumed for illustration.
- Bed
- B
- 0.030
- 0.234
- 0.195
- Result
- reservoir, oil
- Bed
- C
- 0.043
- 0.047
- —
- Result
- non-reservoir: tight
- Bed
- D
- 0.289
- 0.146
- 0.440
- Result
- reservoir, oil (marginal)
- Bed
- G
- 0.626
- 0.050
- —
- Result
- non-reservoir: shaly
- Bed
- E1
- 0.018
- 0.196
- 0.344
- Result
- reservoir, oil
- Bed
- E2
- 0.000
- 0.201
- 1.000
- Result
- reservoir, water
| Bed | Result | |||
|---|---|---|---|---|
| B | 0.030 | 0.234 | 0.195 | reservoir, oil |
| C | 0.043 | 0.047 | — | non-reservoir: tight |
| D | 0.289 | 0.146 | 0.440 | reservoir, oil (marginal) |
| G | 0.626 | 0.050 | — | non-reservoir: shaly |
| E1 | 0.018 | 0.196 | 0.344 | reservoir, oil |
| E2 | 0.000 | 0.201 | 1.000 | reservoir, water |
In the logging report, we mark bed D as productive, with a reservation about the saturation model, and we recommend testing it. Beds B and E1 are productive, and E2 is water-bearing.
Step 8: uncertainty
Each step brings its own uncertainty. It comes from the parameters (the Archie coefficients , , , and , , the matrix and shale densities), the choice of model and relationship, the GR baselines, the cut-offs, and the data themselves (depth matching, corrections, thin beds). The influence is of two kinds. Continuous parameters shift the result smoothly: an error of 10% in changes by 5% of its value at (more). “Yes or no” decisions can include or exclude a marginal bed entirely, and so change the net thickness in a jump. These decisions are the saturation model, the shale-volume relationship and the cut-offs.
- hydrocarbon pore thickness of the bed, , m
- its change, m
- water saturation of the bed, fraction
- error in water saturation (absolute), fraction
Units: dimensionless (relative changes)
- The thickness and porosity of the bed do not change; only does.
- The error is small (linear approximation).
- The bed stays on the same side of the cut-offs. Otherwise its pore thickness changes in a jump, all at once.
The same relative error in costs more the higher the water saturation. With an error of 5% (an error of 10% in at ) the pore thickness changes by 1.25% at , by 5% at and by almost 12% at .
- Base case
- the previous examples: net pay 12.2 m, = 1.75 m
- Variants
- one change at a time: the saturation model, the shale-volume relationship, , , , the cut-offs (table below)
- 10% higher: the of bed B rises from 0.195 to 0.205, and by the formula above its pore thickness falls by about ; the whole falls by 1.8%.
- instead of 2, with recalculated from bed E2 with the same (0.0463 Ω·m): changes by only 0.1%. The error in almost cancels because the porosity of the productive beds is close to that of E2. On the other hand, this is 31% lower than the water sample — the discrepancy itself points to a wrong .
- with from the water sample (0.0667 Ω·m): the of bed D is 0.516 — above the cut-off; the bed drops out, and is lower by 22.5%.
- Archie in bed D: = 0.559, the bed drops out, net pay is 8.4 m, and is lower by 17.8%. Linear shale volume: the of bed D is 0.450 — above the cut-off of 0.35, and the result is almost the same: is lower by 18.6%.
- and : is higher by 4.5% and lower by 4.3%; bed D remains productive.
What it means. That is why the report gives not only the base value but also the alternatives. Most importantly, it states what would reduce the uncertainty: a test of bed D, the water saturation from core cut with oil-based mud, and the cation exchange capacity of the clays. If we set all the parameters to their extreme values at once, the range would be too wide and too improbable. Instead, we assess their joint influence with probabilities (Probabilistic volumetrics by Monte Carlo simulation, Geological and technical uncertainty of a project). The data in this example are assumed for illustration.
- Variant
- Base case
- Bed D
- productive, 0.440
- , m
- 12.2
- —
- Variant
- Bed D saturation by Archie
- Bed D
- non-productive: 0.559
- , m
- 8.4
- −17.8%
- Variant
- Linear shale volume,
- Bed D
- non-reservoir: 0.450
- , m
- 8.4
- −18.6%
- Variant
- 10% higher / lower
- Bed D
- productive, 0.456 / 0.422
- , m
- 12.2
- −1.8% / +1.8%
- Variant
- / , recalculated from bed E2
- Bed D
- productive, 0.429 / 0.451
- , m
- 12.2
- +0.1% / −0.1%
- Variant
- , from the water sample
- Bed D
- non-productive: 0.516
- , m
- 8.4
- −22.5%
- Variant
- /
- Bed D
- productive, 0.411 / 0.466
- , m
- 12.2
- +4.5% / −4.3%
- Variant
- Cut-off 0.40 instead of 0.50
- Bed D
- non-productive: 0.440
- , m
- 8.4
- −17.8%
- Variant
- Cut-off 0.25 instead of 0.35
- Bed D
- non-reservoir: 0.289
- , m
- 8.4
- −17.8%
| Variant | Bed D | , m | |
|---|---|---|---|
| Base case | productive, 0.440 | 12.2 | — |
| Bed D saturation by Archie | non-productive: 0.559 | 8.4 | −17.8% |
| Linear shale volume, | non-reservoir: 0.450 | 8.4 | −18.6% |
| 10% higher / lower | productive, 0.456 / 0.422 | 12.2 | −1.8% / +1.8% |
| / , recalculated from bed E2 | productive, 0.429 / 0.451 | 12.2 | +0.1% / −0.1% |
| , from the water sample | non-productive: 0.516 | 8.4 | −22.5% |
| / | productive, 0.411 / 0.466 | 12.2 | +4.5% / −4.3% |
| Cut-off 0.40 instead of 0.50 | non-productive: 0.440 | 8.4 | −17.8% |
| Cut-off 0.25 instead of 0.35 | non-reservoir: 0.289 | 8.4 | −17.8% |
Each variant changes one decision, and everything else stays as in the base case. The two cut-off rows and the row with the Archie model give the same result: in all three, bed D drops out.
Terms and symbols
- Zonation
- Division of the section into beds by lithology, permeability and fluid. It is the basis of bed-by-bed interpretation.
- Quick-look interpretation
- A fast interpretation after logging, for decisions at the wellsite. The steps are the same, but the parameters are preliminary.
- Bed-by-bed and sample-by-sample interpretation
- A calculation from readings averaged opposite beds, or at every recording depth with the intervals summed afterwards.
- Cut-offs
- Thresholds of shale volume, porosity and water saturation by which reservoir and productive reservoir are identified.
- Net thickness and net pay
- The sum of the reservoir intervals, and the sum of the reservoir intervals with hydrocarbons above the contact.
- Net-to-gross ratio (NTG)
- The ratio of net thickness to gross thickness.
- Hydrocarbon pore thickness
- The volume of hydrocarbons at reservoir conditions per unit area. It equals .
- Fluid type
- The conclusion of the logging report for each bed: oil, gas, water or “unclear”.
- Marginal bed
- A bed with properties near the cut-offs. Whether it enters the net thickness depends on the model and the parameters.
Common mistakes and misconceptions
“The resistivity is high, so it is oil.”
Resistivity rises both with hydrocarbons and with low porosity. A tight streak can be the most resistive bed in the section. Porosity, shale volume, saturation and the signs of permeability together decide productivity.
“The order of the steps does not matter — we will calculate everything anyway.”
Effective porosity needs shale volume, needs porosity, and saturation needs both. A step made too early rests on assumptions that we later forget and never check.
“We will take from the neighbouring field.”
is one number per interval, and its error passes into all the saturations. We bring it to formation temperature and check it in several ways in our own well: against samples, the SP and water-bearing beds.
“We will choose the saturation model that gives more oil.”
We choose the model according to the form of the shale distribution, and we check it on water-bearing beds and on core before anyone looks at the result. Otherwise marginal beds become productive at the interpreter's wish.
“Net thickness is a single number.”
It is the result of a chain of decisions. If one marginal bed changes it by a third, the report gives alternatives and recommends a test that will settle the question.
In depth: advanced detail
Where the cut-offs come from
A cut-off separates rock that practically does not yield fluid under reservoir pressure drawdowns (the pressure drop that pushes fluid to the well) from rock that does. That is why we look for it through permeability. From core we build a porosity–permeability relationship (Reservoir quality: geological controls on porosity and permeability), and we find the porosity at which the permeability falls to the limit. For oil the limit is often taken to be of the order of 1 mD (millidarcy, a unit of permeability), and for gas it is lower. We choose the shale-volume cut-off by the same logic or from test results. We choose the water-saturation cut-off from relative permeabilities: above it, the bed yields mainly water (Relative permeability, Fractional flow function and mobility ratio).
- Relationship from the core of the bed (assumed)
- , in mD
- Permeability limit
- 1 mD; variants 0.5 and 2 mD
- Pore thickness of the beds
- from the examples of the lesson
- At 1 mD: — the adopted cut-off.
- At 0.5 and 2 mD: and .
- What share of the pore thickness the cut-off removes: streak C has m out of 4.094 m of total pore thickness in the beds that passed the shale-volume cut-off (B, C, D, E1, E2). That is 1.4%.
What it means. A cut-off is an agreement with a justification, not a constant of the rock. We check it by how much pore thickness it removes. If the removed streaks contain a noticeable share of the pores, the cut-off needs a special justification, and the result needs alternatives. Here the removed streak contains only 1.4% of the pores. The data in this example are assumed for illustration.
Connections to other topics
- Log acquisition, processing and presentation — how to check the data, tie the runs together and read the heading — step 0.
- Borehole environment: invaded zone and mudcake — the invaded zone, the resistivity profile and the first checks of the borehole.
- Determining shale volume — GR baselines, relationships and their effect on net thickness.
- Porosity from the density log — porosity from density and the shale correction.
- Determining formation water resistivity — all the ways of finding formation water resistivity and how they are cross-checked.
- Archie's equation and saturation of clean reservoirs — Archie's equation and the propagation of errors.
- Water saturation in shaly sands — shaly-sand models and how to choose between them.
- Volumetric estimation of hydrocarbons in place — how net thickness, the averages and the pore thickness enter the estimate of hydrocarbons in place.
- Probabilistic volumetrics by Monte Carlo simulation — a probabilistic estimate instead of running through the extreme cases.
- Interpretation charts: how to read them — charts: how the interpretation steps are done by hand.
Check yourself
- 1
Why is shale volume determined before porosity and saturation?
- A.Without it one cannot calculate the effective porosity of a shaly bed or choose the saturation model
- B.Shale volume is determined last, from saturation
- C.It is the convention in reports
- D.Shale volume affects neither porosity nor saturation
Show the answer
Correct answer: A. Without it one cannot calculate the effective porosity of a shaly bed or choose the saturation model
The effective porosity of a shaly bed is the density porosity minus the contribution of the shale, , and shaly-sand models use directly. Fitting the shale volume to the saturation is a vicious circle.
- 2
The most resistive bed of the section, 45 Ω·m, has a density porosity of 0.04, there is no mudcake on the caliper log, and the resistivity curves of different depths of investigation coincide. What is it most likely to be?
- A.A tight non-reservoir rock
- B.Shale
- C.An oil-bearing reservoir
- D.A gas-bearing reservoir
Show the answer
Correct answer: A. A tight non-reservoir rock
The small amount of water in the low porosity explains the high resistivity here, not oil. The absence of mudcake, and the coincidence of curves of different depths of investigation, say that there is no invasion, that is, the bed is practically impermeable. It will not pass the porosity cut-off, and a saturation calculation for it is meaningless.
- 3
A clean bed 4 m thick: , Ω·m, Ω·m, , . Find and the hydrocarbon pore thickness of the bed.
Show the answer
. The pore thickness is m — under every square metre there is 0.8 m³ of oil at reservoir conditions.
- 4
is overestimated by 10% (). In which bed will the hydrocarbon pore thickness change more, in per cent?
- A.The same in both
- B.In a bed with
- C.In a bed with
- D.In neither: does not affect the pore thickness
Show the answer
Correct answer: B. In a bed with
In both beds will rise by 5% of its value, but the pore thickness is proportional to : , that is −1.25% at and −5% at . Errors in the parameters hit beds with a high water saturation hardest.
- 5
A test confirmed that the bed below the contact is water-bearing, but the model with the adopted parameters gives in it. What should be done?
Show the answer
Do not “clip” the result to 1 (100%). Look for what underestimates the water saturation. may be too low (taken from a shaly bed or from the water of another horizon, or converted to an overestimated temperature). may be too low. Porosity may be too high (a wrong matrix, gas, washouts). may be too high (not corrected for invasion by fresh filtrate). In the shaly-sand model, the shale volume may be too high or too low. Apply the corrected parameters to the whole interval. Otherwise the same error would overestimate the hydrocarbon saturation of the productive beds.
- 6
By Archie's equation, bed D of the assumed well fails the water-saturation cut-off; by the Simandoux model it passes. How should this be reflected in the report?
Show the answer
Give both alternatives: with bed D, a net pay of 12.2 m and a pore thickness of 1.75 m; without it, 8.4 m and 1.44 m (18% less). State that core does not confirm the choice of model, and recommend what will settle the question: a test of bed D, and determination of the water saturation and cation exchange capacity on core. Never choose a model to suit the desired result.