EconomicsUncertainty, risk and decisions Intermediate 18 min read

Expected monetary value and preference theory

The expected monetary value (EMV) of a decision is the average of the net present values (NPV) of its possible outcomes, weighted by their probabilities. The NPV of an outcome is its worth in today's money. We multiply the NPV of each outcome by its probability and add the products. EMV does not predict the result of one decision. It shows what the decision brings on average, if we took it many times.

Why it matters

An exploration well will either find a field or turn out dry, and we do not know in advance which. EMV puts both outcomes into one number. We can compare it with other options: to drill the well ourselves, to pass part of the project to a partner who pays for the well (a farm-out), or to walk away. It also shows at what chance of success drilling stops paying off. But one failure can cost a small company more than the whole average gain is worth. So together with EMV we study the attitude to risk, through the utility function and the certainty equivalent.

Quick refresher

  • EMV =∑jpj NPVj= \sum_j p_j\,\mathrm{NPV}_j over outcomes that exclude each other and together cover all the possibilities (∑jpj=1\sum_j p_j = 1). All the NPVs are at one date, at one rate and in the same kind of money. The risk of failure is included through the probabilities, and the discount rate is not raised for it.
  • For an exploration well, EMV =PgV−C= P_g V - C: the chance of success times the value of the discovery, minus the cost of the well. On average, drilling pays as long as Pg>C/VP_g > C/V. In the example of the lesson the break-even chance of success is 0.13.
  • EMV is an average, not a forecast: one well gives either V−CV - C or −C-C. The expected values of independent wells add up, but the chance that all nn of them are dry is (1−Pg)n(1 - P_g)^n.
  • In a farm-out, a partner pays for the well and gets a share of the project. If both sides assess the chances equally, a farm-out does not create EMV. It only divides the EMV, together with the risk, between the two sides. The point of such a deal lies in the different attitudes of the sides to risk, in different assessments, or in a shortage of money.
  • A risk-averse company (one that dislikes risk) compares the options by expected utility, that is, by the certainty equivalent CE: a guaranteed sum that is as good as the risky option. CE is smaller than EMV. The difference is the risk premium. It grows with the spread of the outcomes and falls with the risk tolerance RR.
  • A large company with many independent projects can almost ignore the risk of a single well (CE ≈ EMV). For a small company the same well can be a stake whose loss threatens ruin. Then it is wiser to take a smaller share in a larger number of projects.
Key relationships
EMV=∑jpj NPVj\mathrm{EMV} = \sum_j p_j\,\mathrm{NPV}_j

the outcomes exclude each other, ∑jpj=1\sum_j p_j = 1

EMV=PgV−C\mathrm{EMV} = P_g V - C

exploration well: a discovery worth VV, or a dry well

Pg∗=C/VP_g^{*} = C/V

break-even chance of success

CE=−R ln⁡∑jpj e−xj/R\mathrm{CE} = -R\,\ln \sum_j p_j\,\e^{-x_j/R}

certainty equivalent for an exponential utility function

P(k)=n!k! (n−k)! Pgk (1−Pg)n−kP(k) = \frac{n!}{k!\,(n-k)!}\,P_g^{k}\,(1 - P_g)^{n-k}

probability of kk discoveries from nn independent wells

Common pitfalls
  • Taking EMV for the likely result of one well.
  • Comparing outcomes valued at different dates, or forgetting the cost of the well in the outcome “success”, or subtracting it twice.
  • Counting a dry well by its probability and also raising the discount rate for the same risk.
  • Including costs that have already been spent, for example for a seismic survey that is already shot.
  • Believing that when EMV > 0 we must always drill, and that a farm-out with a smaller EMV is always a mistake.

After this lesson you can

  • calculate the EMV of a decision from the NPV and the probabilities of all its outcomes, and check that the outcomes exclude each other, cover all the possibilities and are valued at one date
  • calculate the EMV of an exploration well, find the break-even chance of success, and compare the options “drill alone”, “farm out” and “walk away”
  • explain why EMV is an average over many decisions, and estimate the spread of the results of a programme of several wells
  • describe risk-neutral, risk-averse and risk-seeking attitudes through the utility function, and calculate a certainty equivalent
  • explain why companies do not always choose the highest EMV: the size of the stake compared with their resources, the risk of ruin, the working interest (the share of a project that the company takes)

Expected monetary value: the average over the outcomes

Many decisions in the oil and gas business are made before we know how they will end. Will the well find oil? Will the accumulation turn out large or small? Will a new technology work? We describe such a decision by a set of outcomes. For each outcome we need two numbers: a probability and a money result, usually the NPV (Net present value (NPV)). EMV combines them into one number.

Expected monetary value
EMV=∑j=1mpj NPVj,∑j=1mpj=1\mathrm{EMV} = \sum_{j=1}^{m} p_j\,\mathrm{NPV}_j, \qquad \sum_{j=1}^{m} p_j = 1
where:
  • EMV\mathrm{EMV}expected monetary value of the decision, US$ million
  • pjp_jprobability of the jj-th outcome, fraction
  • NPVj\mathrm{NPV}_jnet present value of the jj-th outcome at the date of the decision (the index is the number of the outcome, not a rate), US$ million
  • mmnumber of outcomes, —

Units: the money units of the NPV, for example US$ million in constant prices

Holds when
  • the outcomes exclude each other and together cover all the possibilities, so the probabilities add up to one
  • all the NPVs are calculated at one date (the date of the decision), at one rate and in the same kind of money
  • the NPV includes only the future flows that depend on the decision; costs already spent are not included (what belongs to a decision)
  • the risk of failure is counted by the probabilities; the discount rate is not raised for the same risk (Choosing the discount rate)

EMV is the average value of NPV over all the outcomes, as if the decision were taken many times in the same conditions. By this rule we choose, among several options, the one with the largest EMV. The option “do nothing” has an EMV of zero.

To drill or not to drill: EMV of an exploration well

Take a prospect (a possible drilling target) whose geological chance of success is estimated at 0.30 (how it is estimated). The exploration well costs US$12 million, and this money is spent whatever the outcome. If the well finds an accumulation, the field will be developed as in the library's example project (Net present value (NPV)). The NPV of that project at a rate of 10% is US$100.13 million, counted at the middle of project year 1. That moment comes one year after the decision to drill. So at the date of the decision the discovery is worth 1.11.1 times less.

EMV of an exploration well
EMV=Pg (V−C)+(1−Pg)(−C)=PgV−C\mathrm{EMV} = P_g\,(V - C) + (1 - P_g)(-C) = P_g V - C
where:
  • PgP_gchance of success of the well, fraction
  • VVvalue of the discovery at the date of the decision: the NPV of its development, not counting the cost of the exploration well, US$ million
  • CCcost of the exploration well, spent whatever the outcome, US$ million

Units: US$ million at the date of the decision

Holds when
  • there are two outcomes: a discovery that is developed, and a dry well; the size of the discovery is taken as known (different sizes are covered in the section below)
  • VV and CC refer to one date; if the moment to which the NPV of the project is brought comes tt years after the decision, the NPV is multiplied by (1+i)−t(1 + i)^{-t} (moving the time origin)
  • the tax effects of the cost of the well are not counted (or CC is already taken after tax)

The two ways of writing give the same result. The first lists the outcomes: success brings V−CV - C, and failure brings a loss of CC. The second is shorter: the company pays CC for certain and receives VV with probability PgP_g. When we list the outcomes, it is easy to forget CC in the outcome “success”, or to subtract it twice. The check is that both ways must give the same number.

Worked exampleEMV of an exploration well
Given (assumed data)
Chance of success PgP_g
0.30
Cost of the well CC
12 million dollars
NPV of the development at 10%
100.13 million dollars at the middle of project year 1
From the decision to the middle of project year 1
1 year
Solution
  1. Value of the discovery at the date of the decision: V=100.13/1.1=91.03V = 100.13/1.1 = 91.03 million dollars.
  2. NPV of the outcomes: discovery, V−C=91.03−12=79.03V - C = 91.03 - 12 = 79.03 million dollars; dry well, −12-12 million dollars.
  3. Contributions of the outcomes: 0.30⋅79.03=23.710.30\cdot79.03 = 23.71 and 0.70⋅(−12)=−8.400.70\cdot(-12) = -8.40. EMV =15.31= 15.31 million dollars.
  4. Check with the short form: 0.30⋅91.03−12=15.310.30\cdot91.03 - 12 = 15.31 million dollars.
  5. Break-even chance: Pg∗=12/91.03=0.132P_g^{*} = 12/91.03 = 0.132.
Answer: EMV ≈ 15.31 million dollars > 0: by the EMV criterion, drilling is worth it. On average, drilling pays when the chance of success is above 0.132.

What it means. On average the well returns 15.31 million dollars on top of the 10% return, but this is the average over many such wells. One particular well gives either 79.03 million dollars or a loss of 12 million, and in this example the second is 2.3 times more likely than the first. The margin in probability is large: the estimate of PgP_g may be more than twice too high, and drilling will still pay on average. The data in this example are assumed for illustration.

Break-even chance of success
Pg∗=CVP_g^{*} = \frac{C}{V}
where:
  • Pg∗P_g^{*}chance of success at which the EMV of drilling is zero, fraction
  • C, VC,\ Vcost of the well and value of the discovery at the date of the decision, US$ million

Units: dimensionless

Holds when
  • the same as for the EMV of a well: two outcomes, with VV and CC at one date.

The more expensive the well is compared with the value of the discovery, the more sure we must be of success. The ratio V/CV/C shows how many times the prize is larger than the stake. It tells at what chances drilling still pays on average: at V/C=10V/C = 10, a chance Pg>0.1P_g > 0.1 is enough.

EMV against the chance of success: drill alone, farm out or walk away0.00.10.20.30.40.50.6−10010203040Chance of success PgEMV, US$ milliondrill alonefarm out halfwalk away: EMV = 0Pg* = 0.130.2615.313.7

Chart: the horizontal axis shows the chance of success from 0 to 0.6, and the vertical axis shows EMV from minus 15 to 45 million dollars. The line “drill alone” starts at minus 12 at zero chance, crosses zero at 0.13 and rises to 43 at 0.6. The line “farm out” leaves zero and rises more gently, to 27 at 0.6. The lines cross at 0.26. The points of the example at a chance of 0.30 are marked: 15.3 and 13.7 million dollars. The horizontal zero line is walking away from the project.

CalculatedEMV for the company against the chance of success: drill alone, farm out a half share to a partner who pays for the well, or walk away (EMV = 0). The break-even chance for drilling alone is 0.13. At 0.26 both ways of taking part give the same EMV.

Drill alone, farm out or walk away

The owner of an area does not have to carry the whole risk alone. A common option is a farm-out: a partner pays for the whole exploration well and for this gets a share ww of the project. If the well turns out dry, the owner loses nothing. If it finds an accumulation, the owner keeps the share 1−w1 - w and takes part in the development in proportion to it.

EMV of a farm-out to a partner who pays for the well
EMVw=Pg (1−w) V,Pg,w=CwV\mathrm{EMV}_w = P_g\,(1 - w)\,V, \qquad P_{g,w} = \frac{C}{w V}
where:
  • EMVw\mathrm{EMV}_wEMV of the owner of the area after giving away the share ww, US$ million
  • wwshare of the project given to the partner, fraction
  • Pg,wP_{g,w}chance of success at which drilling alone and a farm-out give the owner the same EMV, fraction
  • Pg, V, CP_g,\ V,\ Cchance of success, value of the discovery and cost of the well, as above, —, US$ million

Units: US$ million at the date of the decision

Holds when
  • the partner pays for the whole well, and the sides carry the development costs in proportion to their shares
  • both sides assess PgP_g and VV in the same way

The difference between the EMV of drilling alone and EMVw\mathrm{EMV}_w is PgwV−CP_g w V - C, which is exactly the EMV of the partner. Above the chance Pg,wP_{g,w}, drilling alone gives the higher EMV. Below it, a farm-out does. But below Pg,wP_{g,w} the EMV of the partner is negative, and with the same assessments the partner will not accept the deal.

Worked exampleHalf of the share for paying for the well
Given (assumed data)
Prospect
as in the example above: Pg=0.30P_g = 0.30, V=91.03V = 91.03 million dollars, C=12C = 12 million dollars
Terms of the deal
the partner pays for the well and receives w=0.5w = 0.5 of the project
Solution
  1. Owner: 0.30⋅0.5⋅91.03=13.650.30\cdot0.5\cdot91.03 = 13.65 million dollars, against 15.31 million when drilling alone.
  2. Partner: 0.30⋅0.5⋅91.03−12=1.650.30\cdot0.5\cdot91.03 - 12 = 1.65 million dollars. This is exactly the EMV that the owner gave away: 15.31−13.65≈1.6515.31 - 13.65 \approx 1.65.
  3. The owner is indifferent (and the partner's EMV is zero) at Pg,w=12/(0.5⋅91.03)=0.264P_{g,w} = 12/(0.5\cdot91.03) = 0.264.
Answer: By EMV, the owner does better by drilling alone: 15.31 million dollars against 13.65. The deal passes 1.65 million dollars of EMV to the partner, and with it the whole risk of a dry well.

What it means. The deal does not create value: with equal assessments, whatever EMV the partner gets, the owner loses. Still, such deals are made all the time. The reasons are different assessments of the chances, the partner being able to drill more cheaply, the owner's shortage of money, and above all the different attitudes to risk: for a small company a loss of 12 million dollars can mean much more than for a large one. How to account for this in numbers is shown in the section on the attitude to risk. The data in this example are assumed for illustration.

More than two outcomes: how large the discovery will be

A discovery is not one number: the accumulation may turn out smaller or larger than expected. If it is too small, the development will not pay and will not be started. For the economics, such a discovery is the same as a failure, although geologically the well is a success. The limit is set by the minimum economic field size (MEFS): the volume at which the NPV of the development is zero. The probability of finding an accumulation not smaller than that is the commercial chance of success PcP_c. It is not larger than PgP_g (from geological to commercial success).

Worked exampleA dry well and three sizes of discovery
Given (assumed data)
Geological chance of success
0.30; cost of the well 12 million dollars
Sizes of the discovery (as a fraction of the base production of the project)
×0.5 with probability 0.3; ×1 with 0.5; ×1.5 with 0.2 (if the well succeeds)
Development model
the library's example project: the production of each year is multiplied by the fraction, the costs stay the same
Solution
  1. NPV of the development at the middle of project year 1: −26.40, 100.13 and 226.51 million dollars. NPV becomes zero at a production of 0.60 of the base, that is about 7.2 million barrels instead of 12. This is the minimum economic field size. The small discovery is below it, and it is not developed.
  2. Outcomes at the date of the decision: the dry well (p=0.70p = 0.70) and the small discovery (p=0.09p = 0.09) each give −12-12 million dollars. The medium one (p=0.15p = 0.15) gives 100.13/1.1−12=79.03100.13/1.1 - 12 = 79.03. The large one (p=0.06p = 0.06) gives 226.51/1.1−12=193.92226.51/1.1 - 12 = 193.92 million dollars.
  3. EMV =0.70⋅(−12)+0.09⋅(−12)+0.15⋅79.03+0.06⋅193.92= 0.70\cdot(-12) + 0.09\cdot(-12) + 0.15\cdot79.03 + 0.06\cdot193.92 =14.01= 14.01 million dollars.
  4. Commercial chance of success: Pc=0.30⋅(0.5+0.2)=0.21P_c = 0.30\cdot(0.5 + 0.2) = 0.21.
Answer: EMV ≈ 14.01 million dollars, with a commercial chance of success of 0.21 and a geological one of 0.30.

What it means. The four outcomes exclude each other, and their probabilities add up to one. This is the first thing to check in such a calculation. The small discovery is not developed: the company loses only the well, and does not add the negative NPV of a development to the loss. If it were developed “since we found it”, EMV would be 2.16 million dollars lower. For the same reason we cannot replace the distribution of sizes by one average discovery. The average size ×0.95 would give an EMV of 11.86 million dollars, which is less than the correct sum over all the outcomes. The data in this example are assumed for illustration. In this simplified model, the size of the discovery changes only the production. In reality the costs depend on it too: a small discovery would be developed more cheaply, and a large one at a higher cost.

EMV is an average over many wells

The meaning of EMV shows itself over many decisions. If we drill many similar wells, the share of discoveries comes close to the chance of success, and the average result per well comes close to EMV. But a company drills not hundreds of wells but a few, and then not only the average matters. It also matters how far the result can differ from the average. The number of discoveries among nn independent wells with the same chance of success follows the binomial distribution.

Probability of kk discoveries from nn independent wells
P(k)=n!k! (n−k)!  Pgk (1−Pg)n−k,k=0,1,…,nP(k) = \frac{n!}{k!\,(n-k)!}\;P_g^{k}\,(1 - P_g)^{n-k}, \qquad k = 0, 1, \ldots, n
where:
  • P(k)P(k)probability that exactly kk of the nn wells are successful, fraction
  • nnnumber of wells in the programme, —
  • kknumber of discoveries, —
  • PgP_gchance of success of one well, the same for all, fraction
  • n!k! (n−k)!\frac{n!}{k!\,(n-k)!}the number of ways to choose kk successful wells out of nn (n!=1⋅2⋯nn! = 1\cdot2\cdots n, 0!=10! = 1), —

Units: dimensionless

Holds when
  • the outcomes of the wells are independent: the prospects share no play risk (a play is a group of prospects in the same geological setting: if a key ingredient is missing there, all of them fail)
  • the chance of success is the same for all wells; with different chances the distribution is found by going through the outcomes
  • the whole programme is drilled without revising it after the first results

The mean number of discoveries is nPgnP_g, and the EMV of the programme is nn times the EMV of one well. The chance that all the wells are dry is P(0)=(1−Pg)nP(0) = (1 - P_g)^n. It falls quickly as nn grows, but for a small programme it stays noticeable.

Worked exampleA programme of five wells
Given (assumed data)
Wells in the programme
5 similar prospects in different plays
Each well
Pg=0.30P_g = 0.30, C=12C = 12 million dollars, the discovery is worth V=91.03V = 91.03 million dollars
Solution
  1. Cost of the programme: 5⋅12=605\cdot12 = 60 million dollars. NPV of the programme with kk discoveries: k⋅91.03−60k\cdot91.03 - 60.
  2. No discoveries: P(0)=0.75=0.168P(0) = 0.7^5 = 0.168, NPV =−60= -60 million dollars.
  3. One discovery: P(1)=5⋅0.3⋅0.74=0.360P(1) = 5\cdot0.3\cdot0.7^4 = 0.360, NPV =31.0= 31.0. Two: P(2)=10⋅0.32⋅0.73=0.309P(2) = 10\cdot0.3^2\cdot0.7^3 = 0.309, NPV =122.1= 122.1 million dollars.
  4. Three discoveries or more: 0.163 in total.
  5. EMV of the programme: ∑kP(k) NPVk=76.55\sum_k P(k)\,\mathrm{NPV}_k = 76.55 million dollars, exactly 5⋅15.315\cdot15.31. The standard deviation of the result (a measure of its spread) is 93.3 million dollars.
Answer: The EMV of the programme is 76.55 million dollars, but with a probability of 17% the company loses all 60 million, and with a probability of 53% it gets no more than 31.0 million dollars.

What it means. The average result of the programme is good, but the spread around it is larger than the EMV itself. In more than half of the cases the programme brings less than half of its expected value, and in one case out of six it brings only a loss. For a company that has no other projects, such a programme is a serious stake. If all five prospects belonged to one untested play, EMV would stay the same, but the probability of a complete failure would be higher (dependent prospects). The data in this example are assumed for illustration.

Possible NPV of a programme of five wells and their probabilities; the EMV of the programme−1000100200300400010203040NPV of the programme, US$ millionProbability, %0 found171 found362 found313 found134 found35 found0.2EMV = 76.55

Bar chart: the horizontal axis shows the NPV of the programme from minus 100 to 400 million dollars, and the vertical axis shows probability in per cent. The bars stand at −60, 31, 122, 213, 304, 395 million dollars (0, 1 … 5 discoveries) and have heights of 17, 36, 31, 13, 3, 0.2 per cent. The vertical dashed line of the EMV at 76.55 million passes between the bars of one and two discoveries.

CalculatedPossible results of a programme of 5 independent wells: the NPV with 0, 1 … 5 discoveries and their probabilities. The vertical line is the EMV of the programme (US$76.55 million), which is not equal to any outcome.

Attitude to risk: the utility function and the certainty equivalent

Compare two options for the same company: to receive a guaranteed US$15 million, or to drill the well of the example, whose EMV is US$15.3 million. By EMV they are almost equal. But with the second option, in seven cases out of ten the company loses US$12 million. For a small company this can mean a reduced work programme or a missed debt payment. The EMV criterion does not see this difference: it treats all the options with the same average in the same way.

Risk-neutral attitude
Options are compared only by the average, that is, by EMV. This is reasonable when each single stake is small compared with the resources and there are many stakes.
Risk aversion
A guaranteed sum is valued more than a risky option with the same average. A company behaves like this when it sells oil at a fixed price below the expected one (the example with the forward sale). A customer does the same when paying a contractor more for a fixed “turnkey” price (one agreed sum for the whole job).
Risk seeking
A risky option is valued more than a guaranteed one with the same average, for the sake of a chance of a big win. This is rare in company decisions, but it happens, for example when a company needs a big discovery at any price.

The attitude to risk is described in numbers by the utility function u(x)u(x). It gives each sum of money its “worth” for the decision-maker. We compare options by the expected utility ∑jpj u(xj)\sum_j p_j\,u(x_j). For a risk-averse company the utility curve flattens as it rises: each next million adds less utility than the previous one, and losing a million takes away more than winning the same million brings.

It helps to turn the expected utility back into money. The certainty equivalent (CE) is the guaranteed sum whose utility equals the expected utility of the risky option: the company does not mind whether it gets this sum for certain or takes the risk. For a risk-averse company, CE is smaller than EMV. The difference EMV−CE\mathrm{EMV} - \mathrm{CE} is called the risk premium. It is the part of the average value that the company is ready to give up for certainty. It is a sum of money, not an addition to the discount rate (the premium on the rate and the certainty equivalent).

Exponential utility function and the certainty equivalent
u(x)=1−e−x/R,CE=−R ln⁡∑jpj e−xj/Ru(x) = 1 - \e^{-x/R}, \qquad \mathrm{CE} = -R\,\ln \sum_{j} p_j\,\e^{-x_j/R}
where:
  • u(x)u(x)utility of the sum xx (dimensionless; the scale of the value does not matter), —
  • x, xjx,\ x_jmoney result, the NPV of the jj-th outcome, US$ million
  • RRrisk tolerance is a parameter of the company: the larger it is, the closer the behaviour is to risk-neutral, US$ million
  • pjp_jprobability of the jj-th outcome, fraction
  • CE\mathrm{CE}certainty equivalent of the option, US$ million
  • ln⁡\lnnatural logarithm, —

Units: xx, RR and CE are in the same money units

Holds when
  • the attitude to risk is the same at any wealth of the company: adding the same guaranteed sum to every outcome adds that sum to CE too
  • RR is set for the company as a whole and is revised together with its size and financial position
  • when RR is much larger than the spread of the outcomes, the function is almost a straight line on this interval, and CE almost equals EMV

The second formula comes from the condition u(CE)=∑jpj u(xj)u(\mathrm{CE}) = \sum_j p_j\,u(x_j). The exponential function is often used in the valuation of exploration projects: it is set by one number RR, and it is easy to explain. Here is what RR means in practice. The bet “win RR or lose R/2R/2 with equal chances” leaves such a company almost indifferent. It would accept a slightly larger win and reject a smaller one.

Worked exampleOne well through the eyes of a small and a large company
Given (assumed data)
Options
drill alone (+79.0 or −12 million dollars) or farm out a half share (+45.5 or 0)
Chance of success
0.30
Risk tolerance
small company, R=30R = 30 million dollars; large company, R=1000R = 1000 million dollars
Solution
  1. Small company, drilling alone: the expected utility is EU=0.3⋅u(79.0)+0.7⋅u(−12)=−0.0658\mathrm{EU} = 0.3\cdot u(79.0) + 0.7\cdot u(-12) = -0.0658. This is less than the utility of a guaranteed zero. From u(CE)=EUu(\mathrm{CE}) = \mathrm{EU} we get CE=−Rln⁡(1−EU)\mathrm{CE} = -R\ln(1 - \mathrm{EU}) =−30⋅ln⁡1.0658=−1.91= -30\cdot\ln 1.0658 = -1.91 million dollars.
  2. The same company, with a farm-out: CE=8.01\mathrm{CE} = 8.01 million dollars, with an EMV of 13.65.
  3. Large company: drilling alone has a CE of 14.45 million dollars, and a farm-out has 13.44 million dollars.
  4. A large partner that takes the share (+33.5 or −12 million dollars): EMV 1.65, CE 1.44 million dollars.
  5. The risk tolerance at which drilling alone stops being acceptable (CE = 0): R≈38R \approx 38 million dollars.
Answer: For the small company, drilling alone is unacceptable (CE −1.91 million dollars), and a farm-out is attractive (CE 8.01). The large company will prefer to drill alone (CE 14.45 against 13.44).

What it means. One and the same prospect, with the same EMV of 15.31 million dollars, can sensibly lead to different decisions. For the small company, the risk premium of drilling alone is 17.2 million dollars, more than the whole EMV. For the large one it is about 0.9 million, and it behaves almost as a risk-neutral company. The deal from the previous section, which is not attractive by EMV, is attractive to both sides by the certainty equivalent: the risk passes to the one for whom it costs less. The data in this example are assumed for illustration.

Exponential utility function at R = 30 US$ million, the expected utility of drilling and the certainty equivalent−20020406080−1.0−0.50.00.51.0Money x, US$ millionUtility u(x)dry well: −12discovery: +79EMV = 15.3CE = −1.9risk premium

Chart: the horizontal axis shows money from minus 20 to 90 million dollars, and the vertical axis shows utility from minus 1 to 1. The utility curve rises steeply on the left and flattens on the right. The outcomes minus 12 million (utility −0.49) and plus 79 million (0.93) are marked on it, and a straight line is drawn between them. On this line, at an EMV of 15.3 million, the expected utility of −0.07 is marked. A horizontal line at this height crosses the curve at −1.9 million, which is the certainty equivalent. The segment between them is labelled as the risk premium.

CalculatedExponential utility function of a small company (R=30R = 30 million dollars) and drilling the well alone: the two outcomes on the curve, the expected utility on the straight line between them at an EMV of US$15.3 million, and the certainty equivalent of US$−1.9 million. The distance between them is the risk premium.

Why companies do not simply maximise EMV

The EMV criterion is right for someone who makes many independent bets, each small compared with their resources. Then random wins and losses cancel each other out, and the total is close to the sum of the EMVs. A real company departs from this ideal for several reasons.

  • The size of the stake. The same well is a small stake for a company with an annual budget of billions of dollars. For a company that has set aside a few tens of millions for exploration, it is an all-in stake.
  • Ruin. The money runs out before the law of large numbers has time to work. A series of failures can stop the programme before the first discovery, even if every well has a positive EMV. In probability theory this is called gambler's ruin.
  • Decisions that do not repeat. A large development project or the purchase of a company happens once in several years, and “the average over many attempts” is an abstraction for it.
  • The interests of those who provide the money. Lenders and shareholders treat the company's risk differently, and the terms of loan agreements and budget limits themselves restrict the loss that is allowed.
Worked exampleThree whole wells or nine one-third shares
Given (assumed data)
Exploration budget
36 million dollars: enough for three wells of 12 million each
Prospects
as in the example above: Pg=0.30P_g = 0.30; the prospects are from different plays, and the outcomes are independent
Option B
instead of three whole wells, a third of the share in nine wells (partners take the rest)
Solution
  1. Option A: all three wells are dry with a probability of 0.73=0.3430.7^3 = 0.343. EMV: 3⋅15.31=45.93\cdot15.31 = 45.9 million dollars.
  2. Option B: the money at risk is the same, 36 million. No discoveries at all: 0.79=0.0400.7^9 = 0.040. EMV: 9⋅15.31/3=45.99\cdot15.31/3 = 45.9 million dollars.
Answer: With the same EMV of 45.9 million dollars, the probability of being left with no discoveries falls from 34 to 4%.

What it means. Splitting the stakes does not change the average, but it sharply reduces the probability of a catastrophe. That is why exploration projects are usually run by consortia: each company takes a share in several prospects and not everything in one. Partnership, insurance and other ways to reduce risk are covered in the topic Risk reduction and diversification. The data in this example are assumed for illustration.

Here is what this means in practice. Large companies with a portfolio of many independent projects take EMV as the main criterion: for them the risk premium of a single well is small. The utility function and the certainty equivalent are used for stakes comparable with the size of the company, and for choosing the working interest. For the same reason, small companies more often take shares and bring in partners, even if they give away part of the EMV.

Terms and symbols

Outcome
One of the consequences of a decision that exclude each other. Each has its own probability and its own NPV.
EMV
The average NPV of the outcomes, weighted by their probabilities (expected monetary value).
Break-even chance Pg∗P_g^{*}
The chance of success at which the EMV of drilling is zero. For two outcomes it is C/VC/V.
Farm-out
A deal in which a partner pays for the work (for example, an exploration well) and gets a share of the project for it.
Utility function u(x)u(x)
The worth of a sum of money for the decision-maker. For a risk-averse decision-maker the curve flattens as it rises.
Certainty equivalent (CE)
The guaranteed sum that is as good as the risky option by expected utility.
Risk premium
The difference EMV−CE\mathrm{EMV} - \mathrm{CE}: the part of the average value that is given up for certainty.
Risk tolerance RR
A parameter of the exponential utility function. The larger it is, the closer the behaviour is to risk-neutral.
Gambler's ruin
The loss of all the money through a series of failures before the positive average has time to show itself.

Common mistakes and misconceptions

Wrong

“The EMV of the well is US$15 million, so it will bring about US$15 million.”

In fact

The well will bring either US$79 million or a loss of US$12 million. EMV is the average over many similar wells. For one well it only shows whether such a decision pays on average.

Wrong

“The chance of a dry well is already in EMV, but to be safe we will also discount at 20% instead of 10%.”

In fact

This counts the same risk twice. The rate reflects the cost of money and the general market risk. The probability of failure is counted in the outcomes, and the attitude to the size of the loss is counted through utility.

Wrong

“The NPV of the successful outcome is the NPV of the development, and that of the dry well is minus the well.”

In fact

The well is paid for in every outcome: the NPV of success is the value of the discovery minus the cost of the well, and both quantities are at the date of the decision. The check: Pg(V−C)−(1−Pg)CP_g(V - C) - (1 - P_g)C must equal PgV−CP_g V - C.

Wrong

“EMV is positive, so we always drill; a farm-out with a smaller EMV is a mistake.”

In fact

For a small company the same well can have a negative certainty equivalent. In the example of the lesson, at R=30R = 30 million dollars, drilling alone gives a CE of −1.9 million, and a farm-out of a half share gives 8.0 million.

Wrong

“US$5 million has already been spent on the seismic survey, so it is included in the EMV of drilling.”

In fact

Costs that are already spent do not depend on the decision and are not part of it. We calculate the EMV of drilling from the future flows, from the cost of the well to the income of the development.

In depth: advanced detail

Certainty equivalent: an approximation and its limits

If the spread of the outcomes is small compared with RR, we can expand the exponential in a series (a sum of powers) up to the quadratic term: e−x/R≈1−x/R+x2/(2R2)\e^{-x/R} \approx 1 - x/R + x^2/(2R^2). Putting this into the formula for CE gives a simple approximation.

Certainty equivalent through the mean and the variance
CE≈EMV−σ22R,σ2=∑jpj (xj−EMV)2\mathrm{CE} \approx \mathrm{EMV} - \frac{\sigma^2}{2R}, \qquad \sigma^2 = \sum_j p_j\,(x_j - \mathrm{EMV})^2
where:
  • σ2\sigma^2variance of the NPV over the outcomes (a measure of the spread); σ\sigma is the standard deviation, (US$ million)²
  • RRrisk tolerance, US$ million
  • EMV, CE\mathrm{EMV},\ \mathrm{CE}expected value and certainty equivalent, US$ million

Units: US$ million

Holds when
  • exponential utility function
  • the spread of the outcomes is small compared with RR (σ≪R\sigma \ll R); for a normally distributed NPV the formula is exact at any spread

The risk premium is proportional to the variance and inversely proportional to the risk tolerance: doubling the spread of the outcomes makes the premium four times larger, and doubling RR halves it. For two outcomes σ2=Pg(1−Pg)V2\sigma^2 = P_g(1 - P_g)V^2: the spread is set by the value of the discovery, not by the cost of the well.

Worked exampleWhen the approximation works and when it does not
Given (assumed data)
Well
EMV 15.31 million dollars, σ=41.7\sigma = 41.7 million dollars
Risk tolerance
1000 and 30 million dollars
Solution
  1. R=1000R = 1000: the approximation is 15.31−1740/(2⋅1000)=14.4415.31 - 1740/(2\cdot1000) = 14.44 million dollars; the exact CE is 14.45.
  2. R=30R = 30: the approximation gives −13.7 million dollars, and the exact CE is −1.9.
Answer: At R=1000R = 1000 million dollars the approximation is almost exact; at R=30R = 30 it is wrong by 12 million dollars.

What it means. The standard deviation of the outcomes of the well is larger than the risk tolerance of the small company, and the expansion in a series stops working. Besides, the distribution of the outcomes is strongly skewed (lopsided): a rare large win and a frequent small loss. The variance punishes a win in the same way as a loss, but the exponential utility does not, so the approximation overstates the risk premium. For the exploration wells of small companies we calculate CE by the exact formula. The data in this example are assumed for illustration.

What share of a project to take

If a company can choose its working interest α\alpha (it pays the share α\alpha of the cost of the well and receives the same share of the value of the discovery), its EMV grows in proportion to α\alpha. The risk premium, by the approximate formula, grows in proportion to α2\alpha^2. So with a small share the risk costs almost nothing, and with a large share it can outweigh the gain. The certainty equivalent then has its highest value at some share smaller than one.

Working interest with the highest certainty equivalent (approximate)
α∗≈R⋅EMVσ2\alpha^{*} \approx \frac{R\cdot\mathrm{EMV}}{\sigma^2}
where:
  • α∗\alpha^{*}the working interest at which the certainty equivalent is highest; if the result is larger than one, it pays to take all, fraction
  • EMV, σ2\mathrm{EMV},\ \sigma^2expected value and variance of the NPV at a share of 100%, US$ million, (US$ million)²
  • RRrisk tolerance, US$ million

Units: dimensionless

Holds when
  • it follows from CE(α)≈α EMV−α2σ2/(2R)\mathrm{CE}(\alpha) \approx \alpha\,\mathrm{EMV} - \alpha^2\sigma^2/(2R) and inherits the limits of that approximation
  • the share divides both the costs and the income in proportion (without paying for the well on behalf of a partner)

The best share grows with the risk tolerance and with EMV, and falls with the spread of the outcomes. The exact value is found by calculating CE at different shares, as in the example.

Worked exampleThe working interest of a small company
Given (assumed data)
Well
as in the example of the lesson: EMV 15.31 million dollars at a share of 100%
Risk tolerance
R=30R = 30 million dollars
Solution
  1. Share 100%: CE −1.91 million dollars; share 50%: 2.01; share 25%: 2.21 million dollars.
  2. Going through the shares gives the highest CE, 2.36 million dollars, at a share of about 34%.
  3. The approximate formula: α∗≈30⋅15.31/1740=0.26\alpha^{*} \approx 30\cdot15.31/1740 = 0.26. This is noticeably smaller, because it overstates the risk premium.
  4. A large company (R=1000R = 1000 million dollars): CE grows up to a share of 100% (14.45 million dollars), and the approximation gives α∗≈8.8\alpha^{*} \approx 8.8, which is more than one.
Answer: The best share for the small company is about 34%, and for the large one it is the whole well.

What it means. The small company does well to give the rest of the share to partners and to put the freed money into similar shares of other, independent prospects. With the same money at risk, the total EMV stays the same, and the risk is much smaller, as in the example “Three whole wells or nine one-third shares”. A farm-out in which the partner pays for the well (CE 8.01 million dollars) is even better for it than a simple share: besides the risk, the partner takes on part of its costs. The data in this example are assumed for illustration.

Certainty equivalent against the working interest, for a small and a large company020406080100−5051015Working interest in the well, %US$ millionhighest CE: 34%EMV of the shareCE, R = 1000CE, R = 30

Chart: the horizontal axis shows the working interest from 0 to 100%, and the vertical axis shows money from minus 5 to 16 million dollars. The dashed straight line of EMV rises from zero to 15.3 million at a share of 100%. The curve of the large company runs almost along it and ends at 14.4. The curve of the small company rises to 2.4 million at a share of about 34% and falls to −1.9 at a share of 100%.

CalculatedCertainty equivalent against the working interest in the well, for a small (R=30R = 30 million dollars) and a large (R=1000R = 1000 million dollars) company. The dashed line is the EMV of the share. For the small company, CE is highest at a share of about 34%.

Connections to other topics

Check yourself

  1. 1

    The chance of success of a well is 0.2, the value of the discovery at the date of the decision is 60 million dollars, and the cost of the well is 9 million dollars. What is the EMV of drilling?

    1. A.12 million dollars
    2. B.3 million dollars
    3. C.10.2 million dollars
    4. D.−9 million dollars
    Show the answer

    Correct answer: B. 3 million dollars

    EMV=0.2⋅60−9=3\mathrm{EMV} = 0.2\cdot60 - 9 = 3 million dollars. By outcomes: success gives 0.2⋅(60−9)=10.20.2\cdot(60 - 9) = 10.2, failure gives 0.8⋅(−9)=−7.20.8\cdot(-9) = -7.2, and the sum is 3. The answer 12 forgets the cost of the well, and 10.2 forgets the dry well.

  2. 2

    With a chance of success of 0.25, a discovery is worth 80 million dollars at the date of the decision. Up to what cost of the well does drilling keep a non-negative EMV?

    1. A.60 million dollars
    2. B.20 million dollars
    3. C.80 million dollars
    4. D.16 million dollars
    Show the answer

    Correct answer: B. 20 million dollars

    EMV =0.25⋅80−C≥0= 0.25\cdot80 - C \ge 0, so C≤20C \le 20 million dollars. The same limit from the other side: at C=20C = 20 the break-even chance is C/V=20/80=0.25C/V = 20/80 = 0.25.

  3. 3

    The EMV of a company drilling alone is larger than its EMV with a farm-out to a partner. Can the farm-out still be a sensible decision?

    Show the answer

    Yes. With equal assessments the deal only moves EMV and risk to the partner, but for a small company a possible loss means more than for a large one. Its certainty equivalent for drilling alone may be smaller than for the farm-out, and even negative. Besides, the sides may have different assessments of the chances and the costs, and the owner may be short of money. We take the decision with the attitude to risk in mind, not by EMV alone.

  4. 4

    Four independent wells each have a chance of success of 0.25. What is the probability that all of them are dry?

    1. A.0.25
    2. B.0
    3. C.0.004
    4. D.0.32
    Show the answer

    Correct answer: D. 0.32

    (1−0.25)4=0.754≈0.32(1 - 0.25)^4 = 0.75^4 \approx 0.32. Almost a third of the programmes of four such wells give no discovery at all, although the expected number of discoveries is one. The answer 0.004 is the probability that all four succeed: 0.2540.25^4.

  5. 5

    Two options have the same EMV of 10 million dollars. A is a guaranteed 10 million. B is +60 million or −40 million with equal chances. Which will a company with an exponential utility function and R=50R = 50 million dollars choose? Estimate the certainty equivalent of option B.

    Show the answer

    CEB=−50ln⁡(0.5 e−60/50+0.5 e40/50)\mathrm{CE}_\text{B} = -50\ln(0.5\,\e^{-60/50} + 0.5\,\e^{40/50}) =−50ln⁡(0.151+1.113)≈−50⋅0.234≈−11.7= -50\ln(0.151 + 1.113) \approx -50\cdot0.234 \approx -11.7 million dollars. The certainty equivalent is negative: a possible loss of 40 million weighs more for such a company than an equally likely win of 60 million. It will choose option A. The risk premium of option B is about 21.7 million dollars.

  6. 6

    What is true for a programme of 10 independent wells, each with an EMV of 2 million dollars?

    1. A.The EMV of the programme is 20 million dollars, but the actual result can differ greatly from this sum
    2. B.The EMV of the programme equals the EMV of one well
    3. C.The programme will almost surely bring about 20 million dollars
    4. D.The EMV of the programme is less than 20 million dollars because of risk
    Show the answer

    Correct answer: A. The EMV of the programme is 20 million dollars, but the actual result can differ greatly from this sum

    Expected values add up: 10⋅2=2010\cdot2 = 20 million dollars. But the result of the programme is the number of discoveries times the value of a discovery, minus the costs, and with a small number of wells it is widely spread around the average. A complete failure is also possible. Risk reduces not the EMV but the certainty equivalent.

Updated: 5 October 2026