Quick refresher
- On a days versus depth curve, the sloping stretches show the bottom of the hole getting deeper. The horizontal stretches are time without deepening: trips (pulling the drill string out and running it in), casing, logging, pressure tests, and also stops caused by complications (problems in the hole) and repairs. Even without complications the bit is on bottom for only about half the time. In well A-2 it is 53.1% of the productive time and 45.5% of the calendar time.
- We divide the calendar time of drilling into productive time and non-productive time (NPT: repairs, complications, accidents and standby, which means waiting). Invisible lost time is slow work inside productive operations. We can see it only by comparing with the best performance or with the technical limit.
- Commercial speed is the metres drilled per rig-month (720 h), counted over the whole calendar time of drilling and casing. Technical speed is the same, counted over the productive time only. Their ratio equals the share of productive time.
- The cost estimate has three parts. Time-dependent costs are the spread rate (the daily cost of the rig and the services) multiplied by the days. Depth- and material-dependent costs are pipe, bits, mud and cement. Lump-sum costs are the site, mobilisation (moving the rig and crew in), logging and completion. Speeding up the work reduces only the first part.
- The cost of a well is skewed to the right (it has a long tail of high costs). A well rarely costs less than planned, and then only a little. It often costs more, and sometimes by a lot. So the mean is higher than the median. We calculate the contingency from a risk register (a list of the events that may happen) and we state its level. The P90 of cost is the sum that will not be exceeded with 90% probability.
- On the learning curve, each new well of a series cuts the excess over the technical limit by the same factor. We decide whether to complete a well or abandon it by the extra cost that this choice adds. The money already spent on drilling is not part of it.
commercial and technical speed, m/rig-month; footage in metres, time in hours
the estimate: lump-sum costs, the spread rate times the number of days, the unit price times the quantity
the mean contingency from a register of independent risks
the learning curve: the duration of the -th well of a series
- Explaining the high cost of a well only by slow drilling. A large part of the money goes on time without deepening and on complications.
- Counting only accidents as non-productive time. It includes repairs, complications and waiting too.
- Adding a “10% for everything” contingency without knowing which risks it covers.
- Confusing the P90 of cost with the P90 of hydrocarbon volumes. The P90 of cost is a high estimate: with 90% probability it will not be exceeded. The P90 of volumes is a low estimate: with 90% probability it will be exceeded.
- Comparing wells by cost per metre without correcting for depth, casing programme and the amount of evaluation.
- Counting the money already spent on drilling in the decision to complete a well.
After this lesson you can
- draw and read a days versus depth curve: the stretches where the hole gets deeper, the time without deepening, and the stops caused by complications
- divide the time of a well into productive time, non-productive time and invisible lost time, and calculate the mechanical, technical and commercial drilling speed
- estimate how long a new well will take from offset wells (nearby wells already drilled), correcting for depth and allowing for non-productive time
- prepare a well cost estimate with time-dependent, depth- and material-dependent and lump-sum costs, split into tangible and intangible; find the cost per metre
- estimate a contingency from a risk register and read the P50 and P90 estimates of cost
- describe the learning curve in a series of wells, and decide “complete or abandon” by the extra cost that the decision adds
The days versus depth curve
The clearest picture of well construction is the days versus depth curve. The horizontal axis shows the days from the start of drilling (spud). The vertical axis shows the depth of the bottom of the hole, measured along the hole. Depth increases downward, as in a geological section. The plan is drawn from the drilling programme, and the actual record from the daily reports. Both lines are kept on one sheet, so any divergence is seen at once.
The curve has two kinds of stretches. On sloping stretches the bottom of the hole gets deeper. This is mechanical drilling, with connections (adding a new stand of pipe to the string). The steeper the stretch downward, the faster the drilling. Horizontal stretches are time without deepening, called flat time in English-language practice. They include trips to change the bit, circulating (pumping mud to clean the hole), well logging, running and cementing casing, waiting on cement (WOC), and installing and pressure-testing the blowout preventers (BOP). The longest “shelves” are at the casing setting depths, because the casing work and the preparation for the next section happen there.
Shelves also appear in the middle of a section, where the plan has none. This is time that was not planned: repairing equipment, dealing with lost circulation (mud flowing away into the rock) or stuck pipe, or waiting on materials. We separate it from the planned time and analyse it on its own, in the next section.
Chart. The horizontal axis shows days from the start of drilling, from 0 to 35. The vertical axis shows depth from 0 to 3000 metres, increasing downward. The solid line descends in steps. Short sloping stretches of drilling alternate with horizontal shelves at depths of 30, 600 and 1900 metres, where the casing strings are run and cemented. In the middle of the sections there are four shelves without deepening: repair of the top drive at 1250 metres, lost circulation at 2330 metres, stuck pipe at 2700 metres and waiting on casing pipe at 2800 metres. The production casing is cemented on day 29.76, followed by 4 days of completion. The dashed line, without these stops, runs to the left and reaches 2800 metres about 4 days earlier.
- Casing completed
- surface casing — on day 3.12 (600 m), intermediate casing — on day 13.90 (1900 m)
- Interval 600–1900 m
- mechanical drilling 142 h and connections 3.8 h; besides these there were trips, logging, casing, a BOP pressure test and a stop to repair the top drive (16 h)
- Time of the interval from the curve: d, or 258.7 h.
- Average rate of deepening over the interval: m/d.
- Rate on the sloping stretches: m/h, or 214 m/d.
- Share of the interval's time when the bottom was getting deeper: %; the rest is shelves: trips, logging, casing, BOP and repair.
What it means. Most of the shelves are necessary work: a well cannot be built without trips, casing and pressure tests. But this is often where a reserve of time hides. Running the casing, testing the BOP and circulating can be done faster or slower, and the report counts all of this as productive time. Doubling the drilling speed is a job for bits and drilling parameters (Bit performance and cost per metre). Cutting the shelves by a third is often easier. The data in this example are assumed for illustration.
Where the time goes: productive, non-productive, invisible losses
To see where the time went, we break it down by type of work. In Russian-language practice this is the calendar time balance of drilling. It lists the time of mechanical drilling, trips, casing and auxiliary work, and, separately, the time of repairs, complications, accidents and standby. Preparatory work, rig-up and the testing of the well are not part of the drilling balance. They are counted in the full cycle of well construction.
- Productive time
- Work without which a well cannot be built: drilling with connections, trips, casing, logging, pressure tests. It is part of the plan.
- Non-productive time (NPT)
- Time that was not in the plan and did not advance construction. It includes equipment repair. It includes dealing with complications: lost circulation, hole collapse, and bit balling (sticky clay packing around the bit). It includes dealing with accidents: stuck pipe (pipe that cannot be moved), tool breakage and tools left in the hole. It also includes waiting on materials, transport, weather or a decision.
- Invisible lost time (ILT)
- Time that could be saved inside productive operations. Stands are pulled more slowly than they could be, a connection takes 8 minutes instead of 4, or a pressure test lasts longer than necessary. The report counts this time as productive, so we can see it only by comparing with the best performance. It is also called hidden NPT, although it is not part of the balance of non-productive time.
- Technical limit and best composite well
- The technical limit is the shortest time in which a well can be built if every operation is executed flawlessly with the available means. Specialists estimate it by analysing the operations. Closer to practice is the best composite well: the sum of the best times of each section or operation in a series of similar wells.
- footage: the metres drilled by the well (or by a group of wells), m
- time of mechanical drilling, with the bit on the bottom, h
- productive time of drilling and casing, h
- calendar time of drilling and casing: productive plus non-productive, h
- hours in a rig-month: 30 days of work of one rig, 24 h each, h
- mechanical speed, the rate of penetration (in the lesson Bit performance and cost per metre, the same quantity for one bit run is ), m/h
- technical and commercial speed, m/rig-month
Units: metres and hours; speeds in m/h and metres per rig-month (m/rig-month)
- and do not include preparatory work, rig-up or testing. A speed that includes them is called the cycle speed.
- For a group of wells, use the total footage and the total time.
- The trip-averaged rate of penetration describes one bit. It is the footage of a bit run divided by the drilling and tripping time of that run (measures of bit performance).
The mechanical speed tells us about the bit and the drilling parameters. The technical speed tells us how well the productive work is organised. The commercial speed covers everything, including accidents and standby. The ratio of the commercial speed to the technical speed is , the share of productive time. So the gap between the two speeds is the price of NPT.
- Type of work
- Mechanical drilling (including coring)
- Hours
- 325.0
- Share, %
- 45.5
- Type of work
- Connections
- Hours
- 8.2
- Share, %
- 1.2
- Type of work
- Trips, circulation, wiper trips
- Hours
- 75.0
- Share, %
- 10.5
- Type of work
- Casing: running the strings, cementing, WOC
- Hours
- 120.0
- Share, %
- 16.8
- Type of work
- Auxiliary: BOP, drilling out, logging
- Hours
- 84.0
- Share, %
- 11.8
- Type of work
- Productive time
- Hours
- 612.2
- Share, %
- 85.7
- Type of work
- Repair of the top drive
- Hours
- 16.0
- Share, %
- 2.2
- Type of work
- Lost circulation (complication)
- Hours
- 44.0
- Share, %
- 6.2
- Type of work
- Stuck pipe (accident)
- Hours
- 30.0
- Share, %
- 4.2
- Type of work
- Waiting on casing pipe (standby)
- Hours
- 12.0
- Share, %
- 1.7
- Type of work
- Non-productive time
- Hours
- 102.0
- Share, %
- 14.3
- Type of work
- Calendar time
- Hours
- 714.2
- Share, %
- 100
| Type of work | Hours | Share, % |
|---|---|---|
| Mechanical drilling (including coring) | 325.0 | 45.5 |
| Connections | 8.2 | 1.2 |
| Trips, circulation, wiper trips | 75.0 | 10.5 |
| Casing: running the strings, cementing, WOC | 120.0 | 16.8 |
| Auxiliary: BOP, drilling out, logging | 84.0 | 11.8 |
| Productive time | 612.2 | 85.7 |
| Repair of the top drive | 16.0 | 2.2 |
| Lost circulation (complication) | 44.0 | 6.2 |
| Stuck pipe (accident) | 30.0 | 4.2 |
| Waiting on casing pipe (standby) | 12.0 | 1.7 |
| Non-productive time | 102.0 | 14.3 |
| Calendar time | 714.2 | 100 |
Completion and testing (96 h) are not part of the drilling balance. Connections are taken at 5 min per 28.35 m stand, as in the lesson Bit performance and cost per metre. The shares are rounded, so their sums may differ by 0.1. The data in this example are assumed for illustration.
- Balance
- mechanical drilling 325 h, connections 8.2 h, trips 75 h, casing 120 h, auxiliary work 84 h; NPT 102 h (table above)
- Footage
- 2800 m
- Best composite well of the area
- 23.45 d of productive time against 25.51 d for A-2 (the table of offset wells in the next section)
- Spread rate of the rig and services
- US$45 thousand/d (section on the cost estimate)
- Productive time: h. With NPT, the calendar time of drilling and casing is h, or 29.76 d.
- Shares: mechanical drilling — %, NPT — %.
- Mechanical speed: m/h. Technical: m/rig-month. Commercial: m/rig-month.
- Check: — the share of productive time, .
- Invisible losses against the best composite well: d. Together with NPT ( d) that is 6.31 d, or US$ thousand.
What it means. NPT is a clear loss, but not the only one. Another 2.06 d went on work that counts as productive time. The best composite well is a benchmark, not a norm. Different crews drilled its sections in different conditions, and it is hard to repeat all the best results in a single well. We can compare speeds only for wells of similar depth and design. In shallow wells the commercial speed is higher simply because trips and casing take a different share of the time. The data in this example are assumed for illustration.
Estimating a new well from offset wells
We almost always estimate a new well from wells already drilled nearby. These are offset wells, with the same casing programme, a similar rock section and, if possible, the same rig. The closer the offsets, the fewer the corrections and the more reliable the estimate. For a new area with no offsets, we build the estimate operation by operation. We take the drilling time of each section from the expected mechanical speed. We take the time of trips, casing and evaluation from norms and from experience in similar conditions.
- 1Select the offsets
Choose wells in the same area or neighbouring ones, with the same casing programme and setting depths and a similar rig. Record the differences: a different mud, bits, contractor or amount of evaluation.
- 2Break down the time
Break the time down by sections and operations, and separate the non-productive time. Carry the productive time over to the new well. Estimate the NPT separately, as a risk.
- 3Adjust to the new well
Recalculate the drilling time for the metres of the new well. Recalculate the time of trips, casing and evaluation for its strings and programme. Allow for the depths, coring and the amount of logging.
- 4Choose the level
For the cost estimate, take the mean or the median of the offsets. For the target set for the crew, take the best composite well or the technical limit.
- 5Add the risks
Add the NPT, taken from its share in the offsets or from a risk register (see the section on contingency). Then convert days into money using the cost estimate.
- Well
- A-1
- 0–600 m
- 3.50
- 600–1900 m
- 9.40
- 1900–2800 m
- 10.90
- NPT
- 2.10
- Well
- A-2
- 0–600 m
- 3.95
- 600–1900 m
- 9.78
- 1900–2800 m
- 11.78
- NPT
- 4.25
- Well
- A-3
- 0–600 m
- 3.75
- 600–1900 m
- 9.05
- 1900–2800 m
- 11.30
- NPT
- 2.30
| Well | 0–600 m | 600–1900 m | 1900–2800 m | NPT |
|---|---|---|---|---|
| A-1 | 3.50 | 9.40 | 10.90 | 2.10 |
| A-2 | 3.95 | 9.78 | 11.78 | 4.25 |
| A-3 | 3.75 | 9.05 | 11.30 | 2.30 |
All three have the same casing programme, core was cut in each, and two suites of logs were run. The values for A-2 are from its time balance. The completion time (4.0 d) is not included in the table. The data in this example are assumed for illustration.
- New well
- the same casing programme, planned depth 2950 m: the last section is 150 m longer
- Addition for 150 m
- drilling at the average speed of the last metres of the offsets, 5.0 m/h including connections; another 6 h for longer trips, wiper trips and casing running
- Completion
- 4.0 d, as in the offsets
- Averages by section: ; ; d.
- Addition for 150 m: h, or 1.50 d; the last section is d.
- Productive time of drilling and casing: d; with completion, 29.97 d.
- NPT of the offsets: on average d per d of productive time, that is 11.8%. For A-4 the allowance is d. The expected duration is d.
- Best composite well: d; with the same addition, 24.95 d of productive time of drilling and casing.
What it means. The base estimate goes into the cost estimate, and the NPT goes into the contingency. This shows how much the work itself costs and how much the risks cost (see the section on contingency). Three offsets are a small sample. One unlucky well shifts the mean noticeably, so we also examine the causes of the NPT and ask whether they will happen again. The target from the best composite well is 1.02 d shorter than the mean estimate. Better organisation of the work can give that much without any new technology. The data in this example are assumed for illustration.
The cost estimate of a well: what depends on time, what on depth
It helps to divide the costs of a well by what makes them grow. Time-dependent costs are charged for each day while the rig works on the well. They include the rate of the drilling contractor for the rig with its crew, and everything else paid by the day: drilling fluids service, the mud logging unit, tool rental, the operator's supervisors, transport, the camp (housing for the crew) and fuel. Their sum is the spread rate of work on the well. Depth- and material-dependent costs grow with the metres of hole and casing: casing pipe, bits, mud materials, cement. Lump-sum costs depend neither on days nor on metres: the site and road, mobilisation and rig-up, wellhead equipment, and service operations paid per job, such as cementing, logging and perforating.
- cost of the well according to the estimate, US$ thousand
- lump-sum costs: the site, mobilisation, wellhead equipment, service operations paid per job, US$ thousand
- spread rate: the rig with its crew and all the services paid by the day, US$ thousand/d
- days of work on the well according to the time estimate, d
- unit price of the -th material: a metre of casing, a bit, a tonne of cement, US$ thousand per unit
- quantity of the -th material — metres of casing, pieces, tonnes, units
Units: any currency; in the example, thousand US dollars and days
- is the number of days from the time estimate. The drilling contract decides how the time of repairing the rig is paid.
- The boundary between the types is not sharp: bits depend on both metres and time, and mud consumption depends on the volume of the hole and on losses.
- Prices are those of the date of the estimate. For a programme lasting several years, we allow for rising prices (escalation).
Speeding up the work reduces only . Changing the casing programme or the depth mainly affects . The set of jobs decides the lump-sum costs, and they hardly depend on how quickly the jobs are done.
The second way to divide the costs is into tangible and intangible costs. Tangible costs create property that stays in the well and keeps its value: casing pipe, the casing head, the Christmas tree (the valves on the wellhead), tubing and the packer. Intangible costs are work and materials that are used up: rig time, services, mud, cement and site preparation. The division comes from accounting. Depreciation (writing off the cost over time) and tax deductions depend on it, and the rules differ from country to country. We do not need it to estimate time and risk, but the estimate usually shows it.
In international practice the approved cost estimate of a well is called the AFE (authority for expenditure). In joint projects the partners approve it in proportion to their working interests (their shares in the project). The operator may exceed it only by an agreed percentage. For a larger overspend it prepares a supplementary AFE. In post-Soviet practice the estimate in the well construction project sets the cost of a well. In essence it is the same calculation of time, materials and lump-sum jobs.
- Item
- drilling rig with crew
- US$ thousand/d
- 28.0
- Item
- drilling fluids service
- US$ thousand/d
- 3.0
- Item
- mud logging unit
- US$ thousand/d
- 1.5
- Item
- rental of tools and equipment
- US$ thousand/d
- 2.5
- Item
- operator's supervisors
- US$ thousand/d
- 1.5
- Item
- transport, camp, communications
- US$ thousand/d
- 5.0
- Item
- fuel
- US$ thousand/d
- 3.5
- Item
- Total
- US$ thousand/d
- 45.0
| Item | US$ thousand/d |
|---|---|
| drilling rig with crew | 28.0 |
| drilling fluids service | 3.0 |
| mud logging unit | 1.5 |
| rental of tools and equipment | 2.5 |
| operator's supervisors | 1.5 |
| transport, camp, communications | 5.0 |
| fuel | 3.5 |
| Total | 45.0 |
That is US$1875 per hour. The rates are assumptions of the example, not data on prices in Kazakhstan.
- Item
- Drilling to the planned depth and logging
- Amount
- Type of cost
- Item
- rig and service time
- Amount
- 1063.80
- Type of cost
- time
- Item
- site, road, pits
- Amount
- 250.00
- Type of cost
- lump sum
- Item
- mobilisation, rig-up and rig-down
- Amount
- 380.00
- Type of cost
- lump sum
- Item
- casing head
- Amount
- 70.00
- Type of cost
- lump sum, tangible
- Item
- cementing of three strings (service)
- Amount
- 90.00
- Type of cost
- lump sum
- Item
- logging, two suites
- Amount
- 190.00
- Type of cost
- lump sum
- Item
- coring and core analysis
- Amount
- 90.00
- Type of cost
- lump sum
- Item
- casing pipe for three strings
- Amount
- 235.20
- Type of cost
- depth and materials, tangible
- Item
- bits
- Amount
- 190.00
- Type of cost
- depth and materials
- Item
- drilling fluid materials
- Amount
- 300.00
- Type of cost
- depth and materials
- Item
- cement and additives for three strings
- Amount
- 70.00
- Type of cost
- depth and materials
- Item
- Production casing and completion
- Amount
- Type of cost
- Item
- rig and service time
- Amount
- 284.85
- Type of cost
- time
- Item
- 168 mm casing pipe
- Amount
- 177.00
- Type of cost
- depth and materials, tangible
- Item
- cementing (service)
- Amount
- 40.00
- Type of cost
- lump sum
- Item
- cement and additives
- Amount
- 40.00
- Type of cost
- depth and materials
- Item
- Christmas tree
- Amount
- 70.00
- Type of cost
- lump sum, tangible
- Item
- perforating, bringing in and testing
- Amount
- 150.00
- Type of cost
- lump sum
- Item
- tubing and packer
- Amount
- 110.00
- Type of cost
- depth and materials, tangible
- Item
- Total
- Amount
- 3800.85
- Type of cost
| Item | Amount | Type of cost |
|---|---|---|
| Drilling to the planned depth and logging | ||
| rig and service time | 1063.80 | time |
| site, road, pits | 250.00 | lump sum |
| mobilisation, rig-up and rig-down | 380.00 | lump sum |
| casing head | 70.00 | lump sum, tangible |
| cementing of three strings (service) | 90.00 | lump sum |
| logging, two suites | 190.00 | lump sum |
| coring and core analysis | 90.00 | lump sum |
| casing pipe for three strings | 235.20 | depth and materials, tangible |
| bits | 190.00 | depth and materials |
| drilling fluid materials | 300.00 | depth and materials |
| cement and additives for three strings | 70.00 | depth and materials |
| Production casing and completion | ||
| rig and service time | 284.85 | time |
| 168 mm casing pipe | 177.00 | depth and materials, tangible |
| cementing (service) | 40.00 | lump sum |
| cement and additives | 40.00 | depth and materials |
| Christmas tree | 70.00 | lump sum, tangible |
| perforating, bringing in and testing | 150.00 | lump sum |
| tubing and packer | 110.00 | depth and materials, tangible |
| Total | 3800.85 |
Casing pipe by the length of the strings: conductor 426 mm — 30 m at US$140/m; surface casing 324 mm — 600 m at US$100/m; intermediate 245 mm — 1900 m at US$90/m; production 168 mm — 2950 m at US$60/m. The prices and rates are assumptions of the example.
- Time
- 25.97 d of drilling and casing without NPT and 4.0 d of completion (the example above); running and cementing the production casing take 2.33 d
- Spread rate
- US$45 thousand/d (table above)
- Other items
- from the table of the estimate
- Days by phase: drilling to the planned depth with logging — d; production casing and completion — d.
- Time-dependent costs: and US$ thousand.
- Pipe: US$ thousand for the three strings and US$ thousand for the production casing.
- Phases: drilling with logging — 2929.0 US$ thousand, casing and completion — 871.85; the completed well — 3800.85 US$ thousand.
- By type: time — 1348.65 (35.5%), lump-sum — 1330 (35.0%), depth and materials — 1122.2 US$ thousand (29.5%). Tangible — 662.2 US$ thousand (17.4%).
- Cost per metre of the well: US$ thousand/m, or US$1288/m (US$393 per foot).
What it means. A day of NPT costs US$45 thousand for time alone. So we count the contingency for risks (the next section) first of all in days. The cost per metre, US$1288/m, is good for comparing similar wells, but not different ones. In a shallow well the lump-sum costs are divided among fewer metres, and a complex well has more strings and more evaluation. Do not confuse it with the cost per metre drilled in a bit run. That figure answers a different question: which bit to use and when to change it (cost per metre drilled). The data in this example are assumed for illustration.
Contingency for risks: the risk register, P50 and P90
The base estimate assumes that everything goes without complications. This does not always happen, and the estimate is wrong in a lopsided way. A well cannot be drilled much faster than planned, because the technical limit bounds the time from below. But lost circulation, stuck pipe or a long wait can add a day or a week. So the distribution of the cost of a well is skewed to the right. A well rarely costs less than planned, and then only a little. It often costs more, sometimes much more. The mean is therefore greater than the median.
The simplest contingency (a reserve for unplanned costs) is a percentage of the base, the same for all wells. It says nothing about where an overspend comes from or how to reduce it. A more exact way is to compile a risk register. It lists the events that may happen, their probabilities and their consequences in days and money. We take the probabilities from the history of the area, from the same analysis of the NPT of the offsets.
- extra cost if the -th event happens, US$ thousand
- spread rate, US$ thousand/d
- time lost, d
- direct cost of the event: materials, fishing (recovering stuck or lost tools), tools left in the hole, US$ thousand
- probability of the event on this well, fraction
- mean (expected) overspend, US$ thousand
Units: thousand US dollars and days
- The events are independent: each happens at most once, and its consequences do not depend on the others. Linked events are combined, or they are given by a conditional probability. An example is lost circulation, after which stuck pipe is more likely.
- The register is incomplete, so we add a contingency for what it does not cover.
- Means add up whatever the relation between the events, but P90 values do not. We find the P90 of a sum from the whole distribution, by listing the combinations or by simulation (why P90 values are not added).
The mean contingency is the sum of the contributions of the events. It shows which event costs the most on average, so measures to reduce risk start with that event. But a mean overspend does not protect against a large one. For that we look at the upper estimates of the distribution.
- Event
- lost circulation in the 2250–2450 m interval
- Probability
- 0.30
- Days
- 3.5
- Direct, US$ thousand
- 80
- If it happens, US$ thousand
- 237.5
- Event
- stuck pipe in the 215.9 mm hole
- Probability
- 0.12
- Days
- 6.0
- Direct, US$ thousand
- 300
- If it happens, US$ thousand
- 570.0
- Event
- caving and hole tightening: reaming (opening the hole up again)
- Probability
- 0.30
- Days
- 1.5
- Direct, US$ thousand
- 0
- If it happens, US$ thousand
- 67.5
- Event
- waiting on materials and transport
- Probability
- 0.25
- Days
- 2.0
- Direct, US$ thousand
- 0
- If it happens, US$ thousand
- 90.0
| Event | Probability | Days | Direct, US$ thousand | If it happens, US$ thousand |
|---|---|---|---|---|
| lost circulation in the 2250–2450 m interval | 0.30 | 3.5 | 80 | 237.5 |
| stuck pipe in the 215.9 mm hole | 0.12 | 6.0 | 300 | 570.0 |
| caving and hole tightening: reaming (opening the hole up again) | 0.30 | 1.5 | 0 | 67.5 |
| waiting on materials and transport | 0.25 | 2.0 | 0 | 90.0 |
The last column is the days at US$45 thousand per day plus the direct costs. The probabilities and consequences are assumptions of the example, consistent with the NPT of the offsets.
- Base estimate
- US$3800.85 thousand (example above)
- Risks
- four independent events from the table above
- Cost of the events: lost circulation ; stuck pipe ; reaming ; waiting US$ thousand.
- Mean overspend: US$ thousand. On average this is 2.72 d of NPT, close to the 2.88 d in the offsets.
- Distribution: there are 16 combinations of events, and the most probable is none at all (). The cumulative probability (the chance that the overspend is this amount or less) reaches 0.570 at US$90 thousand; this is P50. It reaches 0.814 at 305 (P80), and 0.924 at US$570 thousand, where the pipe sticks (P90).
- Estimate to P90: US$ thousand. The contingency is 15.0% of the base. The “10% for everything” rule would give US$380 thousand and would cover only 86% of outcomes.
What it means. The mean (182.4) is twice the median (90). In most outcomes the overspend is small, but a rare stuck pipe costs US$570 thousand and pulls the mean up. Its probability is only 0.12, yet it accounts for 38% of the mean overspend. It alone decides the P90: without stuck pipe the overspend would not exceed US$395 thousand. So it pays better to lower the probability of stuck pipe than to fight frequent but small delays. We can do this by choosing the mud, the drilling parameters and the assembly. The “10%” rule does not cover P90 here, and the risk register shows why. Company policy decides which level to approve: P50, P80 or P90. The higher the level, the less often supplementary AFEs are needed, but the more money is frozen in the contingency. The data in this example are assumed for illustration.
Step chart. The horizontal axis shows the overspend above the base estimate, from 0 to 1100 thousand dollars. The vertical axis shows the cumulative probability, from 0 to 100 per cent. The step at zero rises at once to 32 per cent, which is the probability that no event happens. Then the curve rises in steps and reaches 100 per cent at 965 thousand. Vertical lines mark P50 at 90, the mean at 182 and P90 at 570 thousand dollars.
The learning curve in a series of wells
When the same rig drills a series of similar wells in one area, each new well is usually built faster. The crew learns the rock section and its dangerous intervals. The drilling programme is refined with experience. The best practices pass from shift to shift, and the services and supply adjust to the rhythm. The gain is large at first and then gradually fades. The time approaches a limit set by the operations themselves.
- duration of the -th well of the series, d
- number of the well in the series: 1, 2, 3 …, —
- by how much the first well exceeds the limit: , d
- rate of learning, —
- the limit that the time approaches with full learning, d
Units: days
- The wells are of one type in one area, with one rig and one contractor. A break in the work, a change of crew or a change of casing programme sets the series back.
- We fit the constants to the actual wells of the series. It is more reliable to estimate separately, from the technical limit or the best composite well (fitting the curve).
- Non-productive time improves less with learning than productive time, so it is often analysed separately.
The formula gives . So each well reduces the excess over the limit by the same factor. For the excess falls by 39% per well, and for by 18%.
- Series
- after the discovery by well A-4, 8 production wells about 2800 m deep are drilled from one pad (a site with several wellheads) with the same rig. The time is counted from spud to the move to the next wellhead
- First four wells
- 22.4; 18.2; 16.0 and 14.9 d
- Technical limit
- d — an estimate by specialists from the operations for this casing programme
- Logarithms of the excess over the limit : ; ; ; . The model says they lie on a straight line .
- We fit the line by least squares (the line closest to all the points), with : , , , . The slope is , whence .
- The intercept: , d.
- Forecast: d; likewise , , d.
- The whole series: d against d if all the wells were drilled like the first.
What it means. Each well of the series removes % of the remaining excess over the limit. So after four wells there is almost nothing left to gain: the eighth is only 0.22 d longer than the limit. The forecast is only as good as the limit is right. With another limit, the same four points give other values of and , and another forecast (see the advanced section). The comparison with “drilling like the first well” shows the price of learning, but it is not a target. We make the estimate for the series from the curve, not from the first well. The data in this example are assumed for illustration.
Chart: the number of the well in the series from 1 to 8 horizontally, the duration from 10 to 25 days vertically. Four points for the actual wells: 22.4; 18.2; 16.0 and 14.9 days. A smooth curve passes near them and flattens towards the limit: 14.07 days for the fifth well and 13.22 for the eighth. The lower dashed line is the technical limit of 13 days, the upper one is 22.4 days, the time of the first well.
Dry hole and completed well
It is useful to divide the cost estimate of an exploration or appraisal well into phases, by the decision that is made at the bottom. Drilling to the planned depth, with logging, is paid for in any outcome. Then comes the decision. If the formation has met expectations, the crew runs the production casing and completes the well. If not, it abandons the well: it sets cement plugs and restores the site. The dry hole cost is drilling plus abandonment. The completed well cost is drilling plus casing and completion.
- the value of the well's production: the NPV (net present value, the value today) of its future cash flows, leaving out the costs already spent and the cost of completion, US$ thousand
- the cost of the production casing and completion, US$ thousand
- the cost of abandonment that will be avoided if the well is completed, US$ thousand
Units: thousand US dollars at the date of the decision
- The cost of drilling to the planned depth has already been spent and does not depend on the decision, so it is not part of the comparison (sunk cost).
- The abandonment of a completed well at the end of its life is included in . It comes years later, so it weighs less after discounting (converting future money into today's value).
- If the well is also needed for other purposes, such as injection or observation, add their value to .
We decide on the increment. Completion pays if the production of the well is worth more than the extra cost of completing it compared with abandoning it.
- Item
- rig and service time
- Amount
- 90.00
- Type of cost
- time
- Item
- cement plugs (service and materials)
- Amount
- 60.00
- Type of cost
- lump sum
- Item
- site restoration
- Amount
- 60.00
- Type of cost
- lump sum
| Item | Amount | Type of cost |
|---|---|---|
| rig and service time | 90.00 | time |
| cement plugs (service and materials) | 60.00 | lump sum |
| site restoration | 60.00 | lump sum |
2.0 d of rig work on cement plugs; the rates are assumptions of the example.
- Estimate by phase
- drilling with logging 2929.0, casing and completion 871.85, abandonment 210 US$ thousand
- Log result
- the formation is thinner than expected; the NPV of the well's production without the cost of completion is US$1200 thousand (an assumption of the example)
- The completed well: US$ thousand. The dry hole: US$ thousand, or 82.6% of the completed one.
- The extra cost of completion over abandonment: US$ thousand.
- Comparison: , so we complete the well. The gain from the decision is US$ thousand.
What it means. It is a mistake to compare US$1200 thousand with the full cost of US$3800.85 thousand. US$2929.0 thousand has already been spent, and abandoning the well does not bring it back. The well project as a whole will make a loss, but the decision to complete reduces the loss by US$538.15 thousand. The same logic applies in the economics of exploration. In a failure the company loses the cost of a dry hole, US$3139.0 thousand. The cost of completion belongs to the “success” outcome, as part of the development costs (EMV of an exploration well). The data in this example are assumed for illustration.
Terms and symbols
- Days versus depth curve
- The depth of the bottom of the hole against the days from the start of drilling. Sloping stretches are deepening; horizontal ones are time without deepening.
- Time without deepening (flat time)
- Trips, casing, WOC, logging, pressure tests and completion: everything that happens while the bottom of the hole is not getting deeper.
- Non-productive time (NPT)
- Repairs, complications, accidents and standby: time that was not in the plan.
- Invisible lost time (ILT)
- Slow execution of productive operations, compared with the best performance or the technical limit.
- Technical limit, best composite well
- The technical limit is the shortest time with flawless execution. The best composite well is the sum of the best times of the sections in a series of similar wells.
- Technical and commercial speed
- Metres per rig-month (720 h), counted over the productive time and over the whole calendar time of drilling and casing.
- Spread rate
- The sum of all the costs charged for a day of work on the well: the rig with its crew and the services paid by the day.
- AFE, supplementary AFE
- The approved budget of a well, and the approved increase of it in case of an overspend.
- Tangible and intangible costs
- Tangible costs buy property that stays in the well (pipe, wellhead equipment). Intangible costs pay for work and consumable materials.
- Contingency, P50 and P90 of cost
- An addition to the base estimate for events that it does not account for. P50 and P90 are the sums that will not be exceeded with a probability of 50% and 90%.
- Learning curve
- The reduction of time from well to well in a series. The Brett–Millheim model is .
- Dry hole cost
- Drilling to the planned depth with evaluation, plus abandonment.
Common mistakes and misconceptions
“The well is expensive because it was drilled slowly — we need better bits.”
Mechanical drilling takes less than half of the time (in well A-2, 45.5%). Drilling twice as fast would have shortened the well by 6.8 d out of 29.8. The shelves and the non-productive time offer just as large a reserve of time.
“Non-productive time means accidents.”
NPT includes equipment repairs, complications and waiting for materials or a decision. In well A-2 only the stuck pipe was an accident, and it was less than a third of the time lost.
“We put in a 10% contingency, as always.”
We calculate the contingency from the risk register. It shows which risk is the most expensive and lets us choose the level: P50, P80 or P90. A percentage “for everything” may match the calculation by chance, but it will not show how to reduce the overspend.
“The P90 of an estimate is an optimistic figure, like the P90 of hydrocarbon volumes.”
For costs P90 is the sum that will not be exceeded with 90% probability: a high, cautious estimate. The convention for volumes is the opposite.
“The production of the well is worth less than we have spent on it — let us abandon it.”
The money spent on drilling cannot be recovered whatever we decide. We compare the value of the production with the increment of cost: completion minus abandonment.
In depth: advanced detail
How the learning curve is fitted and why the limit is set separately
If the limit is known, the model becomes a straight line: . We find the two remaining constants by least squares, as in the example of the lesson. It is unreliable to fit all three constants at once to four or five wells. Curves that stay close to the data can be obtained with very different limits, and the forecast for the distant wells depends on the limit most of all.
- Wells of the series
- 22.4; 18.2; 16.0 and 14.9 d, as in the example of the lesson
- Limit
- d instead of 13
- : 2.434; 1.974; 1.609; 1.361. , .
- The slope is , ; , d.
- Forecast: , , , d. The four wells together take 50.54 d against 54.29 with a limit of 13.
What it means. Both curves pass close to the four wells. The largest deviation is 0.28 d for a limit of 13 and 0.57 d for a limit of 11, so four points cannot tell us which limit is right. Yet the forecasts differ by 3.75 d, about US$169 thousand. So we estimate the limit separately, by analysing the operations or from the best wells of the neighbours. We refine the forecast as the series continues. The data in this example are assumed for illustration.
Probabilistic estimation of time
The risk register describes rare events. But ordinary operations also vary in duration: the mechanical speed changes from well to well, and running a casing string goes now faster, now slower. A full probabilistic estimate gives each operation a distribution of duration. The duration is never shorter than the technical limit, and the distribution has a long tail to the right. The estimate adds the events from the risk register and combines everything by Monte Carlo simulation (many random trials; Probabilistic volumetrics by Monte Carlo simulation). The result is a distribution of time and cost, with P10, P50, P90 and the mean.
The links between operations matter. If a crew works slowly, all its operations are slow. If the rock is harder than expected, all the sections are drilled more slowly. Such links widen the distribution of the total: the P90 of a well with linked operations is higher than with independent ones. A model without links gives a deceptively narrow range.
Connections to other topics
- How a well is drilled: the process and the people involved — the stages of well construction, the drilling programme and the types of drilling contract.
- Bit performance and cost per metre — mechanical and trip-averaged speed, the cost per metre of a bit run and the moment to pull the bit.
- Drilling rig: power and hoisting systems — tripping operations and the work of the hoisting system.
- Primary cementing — what makes up the time of cementing and of waiting on cement.
- Expected monetary value and preference theory — the cost of a dry hole in the evaluation of exploration.
- Unit costs per barrel — how well costs enter the capital expenditure per barrel.
- Risk reduction and diversification — how the risk of an overspend is passed to the contractor or an insurer and shared with partners.
Check yourself
- 1
On the actual days versus depth curve, a horizontal shelf of one and a half days has appeared in the middle of a section, far from a casing setting depth. It was not in the plan. What does it most likely mean?
- A.The rock is soft at this point, and drilling was fast
- B.Running the next casing string
- C.An error in the depth measurement
- D.Time without deepening that was not planned: a repair, a complication or waiting
Show the answer
Correct answer: D. Time without deepening that was not planned: a repair, a complication or waiting
A horizontal stretch is time when the bottom of the hole was not getting deeper. Planned shelves are at casing setting depths and at places where the bit is changed. A long shelf in the middle of a section that is not in the plan is almost always non-productive time. We look for its cause in the daily report.
- 2
A well 3400 m deep was drilled and cased in 42 calendar days, of which 5 days were non-productive time. Find the commercial and technical drilling speed.
Show the answer
The calendar time is h, and the productive time is h. The commercial speed is m/rig-month. The technical speed is m/rig-month. Their ratio is the share of productive time.
- 3
Which costs in a well estimate grow primarily with the number of days of work?
- A.The rate of the rig with its crew and the services paid by the day
- B.Mobilisation and rig-up
- C.The Christmas tree
- D.Casing pipe
Show the answer
Correct answer: A. The rate of the rig with its crew and the services paid by the day
The spread rate is charged for each day. It covers the rig with its crew, drilling fluids service, mud logging, tool rental, supervisors, transport and fuel. Pipe depends on the length of the strings. The tree and mobilisation are lump-sum costs.
- 4
A risk register includes an event with a probability of 0.2: it adds 4 d at a spread rate of US$50 thousand per day and US$100 thousand of direct costs. What is its contribution to the mean contingency? Why is the estimate to P90 usually larger than the base plus the mean contingency?
Show the answer
If the event happens, it costs US$ thousand. Its contribution to the mean contingency is US$ thousand. The mean contingency is the average over all outcomes. P90 is the sum that is exceeded in only one case out of ten. The distribution of the overspend is skewed to the right. Its upper part is made up of combinations of several events, or of one large event. So the P90 of the overspend is greater than the mean.
- 5
A learning curve has been fitted to a series of wells: d, , d. How long will the third well take, and what does the time tend to?
Show the answer
d. As the well number grows, the exponential tends to zero, and the time tends to the limit d. The first well takes d.
- 6
A well has been drilled to the planned depth for US$2.6 million. Completion will cost another US$0.7 million and abandonment US$0.2 million. The NPV of the well's production without the cost of completion is US$0.6 million. What should be done?
- A.Complete: 0.6 million is more than 0.7 − 0.2 = 0.5 million
- B.Abandon: 0.6 million is less than the cost of completion, 0.7 million
- C.Abandon: 0.6 million is less than 2.6 + 0.7 million
- D.It makes no difference: the project is loss-making whichever is decided
Show the answer
Correct answer: A. Complete: 0.6 million is more than 0.7 − 0.2 = 0.5 million
The 2.6 million is already spent and does not depend on the decision. Completion adds US$ million to the costs compared with abandonment and brings 0.6 million — a benefit of US$0.1 million. The well as a whole makes a loss, but completion reduces the loss.
Updated: 28 October 2026