Skip to content
Brent$104.61Gas TTF$906USD446.56 ₸
MunaiHub

Drilling cost per metre

Cost per metre of a bit run: the bit cost plus the rig time (rotating, connections, trip), divided by the footage; rate of penetration and cost of the run.

Formula
C = (C_b + C_r · (t_r + t_c + t_t) / 24) / ΔHv_m = ΔH / t_r

Enter money in any currency — the result is in the same currency. Pull the bit when the running cost per metre stops falling. When comparing bits, use the trip time for the same depth.

Source: Bourgeois et al., Applied Drilling Engineering (SPE, 1986), ch. 1: the drilling cost equation

Inputs

You can change a field's unit: the value is converted to the formula's units automatically.

C_bKZT
C_rKZT/day

Rig plus the services paid by time.

t_r
t_c
t_t
ΔH
Unit converter for this formulaTime · Length · Velocity
  • s1
  • min0.0166667
  • h0.000277778
  • d1.15741·10⁻⁵
  • yr3.17098·10⁻⁸

A day is 24 h, a year 365 days.

All units
Result
CCost per metre
Fill in all fields
  • C_ftCost per foot
    KZT/ft
  • v_mRate of penetration
  • C_runCost of the run
    KZT

Results are engineering estimates from standard formulas; for design decisions check them against the codes, project documents and specialists' calculations. The formulas carried over from the original set are unchanged, and their errors are described in the notes.